CITY OF EVERETT SPECIAL PROVISIONS ' <br /> 1 <br /> a. Volumes of Zone A and Zone B material for each watermain alignment. <br /> b. Anticipated volumes of Zone B (excess) material to be taken off-site. <br /> c. Methods of placing Zone A and Zone B material. <br /> d. Method of meeting erosion control requirements. <br /> e. Location of stockpile sites. <br /> Provide a copy of the Soil Management Plan at the Pre-Construction Conference. <br /> 2-10.4 Measurement <br /> Bid items of Work completed pursuant to the Contract Documents will be measured as <br /> described in Division B — Bid Item Descriptions of these Special Provisions and Section 1- <br /> 09 MEASUREMENT AND PAYMENT of the Standard Specifications. <br /> 2-10.5 Payment <br /> Zone A and B material excavation, stockpiling, backfilling and compaction shall be incidental <br /> to pipe and structure costs. <br /> The cost for excavation, haul and disposal of material removed from the site as excess or <br /> unsuitable material will be incidental to the cost of the material that it will replace its volume. <br /> Bid items of Work completed pursuant to the Contract Documents will be measured as <br /> described in Division B — Bid Item Descriptions of these Special Provisions and Section 1- <br /> 09 MEASUREMENT AND PAYMENT of the Standard Specifications. <br /> 2-11 TRIMMING AND CLEANUP ' <br /> 2-1t3 Construction Requirements <br /> Supplement 2-11.3 by adding the following after item 6: <br /> 7. Keep City streets clean and free from mud, dirt and other debris. <br /> Further supplement 2-11.3 by adding the following: <br /> Keep the Project site in a neat and orderly condition during the process of construction <br /> with as little disruption to the adjoining properties as practical under the conditions. <br /> Promptly and as often as needed cleanup debris resulting from Contractor's operations <br /> from drainage facilities such as inlets, catch basins, culverts and open ditches. <br /> Remove and dispose of all construction stakes. <br /> Upon Project completion, clean Project area and neatly dress slopes to present a <br /> uniform appearance blending into the contour of adjacent properties. Remove trash of <br /> all kinds resulting from construction operations. <br /> 2-11.4 Vacant <br /> Revise 2-11.4 to read as follows: <br /> 2-11.4 Measurement <br /> Delete all paragraphs in 2-11.4 and substitute the following: <br /> Bid items of Work completed pursuant to the Contract Documents will be measured as <br /> described in Division B — Bid Item Descriptions of these Special Provisions and Section <br /> 1-09 MEASUREMENT AND PAYMENT of the Standard Specifications. <br /> 111 <br /> 2-11.5 Payment <br /> Delete all paragraphs in 2-11.5 and substitute the following: <br /> Payment for bid items of Work completed pursuant to the Contract Documents will be <br /> as described in Division B — Bid Item Descriptions of these Special Provisions and <br /> Section 1-09 MEASUREMENT AND PAYMENT of the Standard Specifications. <br /> Water Main Improvement"U" Division 2-EARTHWORK October 1, 2019 <br /> WO No.-UP3698 SP-142 <br />