CITY OF EVERETT SPECIAL PROVISIONS
<br /> This lump sum bid item includes the maintenance and protection of traffic control materials,
<br /> tools, and equipment necessary to accomplish the Work in accordance with 1-10.3(2)
<br /> TRAFFIC CONTROL PROCEDURES, including and not limited to, signs, barricades, cones,
<br /> flashers, reader boards, and temporary pavement markings.Also included is cost associated
<br /> with preparation and distribution of public notices involving parking, street access or traffic
<br /> 1 issues.
<br /> Bid Item 7 - Trench Excavation Safety Systems
<br /> Measurement and Payment: Lump Sum (LS)
<br /> Measurement for trench excavation safety systems shall be the ratio of pipe installed and
<br /> backfilled to the total quantity of pipe listed on the Proposal.
<br /> 1 The lump sum bid item includes the costs directly allocated to the safety system for trenches
<br /> and all other excavations including, but not limited to, shoring, benching, bracing, excavation,
<br /> sheeting, and trench box. This Work shall be accomplished in accordance with Divisions 1,
<br /> 2, 7, and 8 of the Standard Specifications and these Special Provisions. Payment per lump
<br /> sum includes all equipment, materials, labor, installation, and removal, and all other work
<br /> required to meet the trench excavation and safety system requirements.
<br /> Bid Item 8 - Street Cleaning and Sweeping
<br /> Measurement and Payment: Unit Price per Hour (HR)
<br /> The unit price per hour for Street Cleaning & Sweeping shall be full compensation for all
<br /> labor, tools, incidentals, and equipment necessary to provide the street sweeping, cleaning,
<br /> and dust control water required for this project.
<br /> Measurement for street sweeping and cleaning will be by the hour for the actual time
<br /> consumed in pavement sweeping, cleaning and debris removal. No allowance will be made
<br /> for time consumed in making repairs to the equipment or for moving the equipment to or from
<br /> the site on which the street cleaning is ordered. No separate payment will be made for water
<br /> required for dust control and the normal operation of the pickup sweepers.
<br /> Bid Item 9 - Erosion/Water Pollution Control
<br /> Measurement and Payment: Force Account (FA)
<br /> This Force Account bid item shall be accomplished in accordance with 1-09.6 FORCE
<br /> ACCOUNT; except, as modified below.
<br /> Erosion/Water Pollution Control, Force Account, shall constitute full compensation for all
<br /> labor, materials, tools and equipment necessary and incidental for the installation,
<br /> maintenance and removal of the temporary erosion and sedimentation control (TESC)
<br /> facilities to prevent pollution, erosion, siltation, and damage to any wetland, stream, other
<br /> watercourse, or surrounding property throughout the life of the Contract. TESC facilities shall
<br /> include, but not be limited to, any cover measures, runoff control measures, soil and site
<br /> stabilization measures, silt fencing as shown on the Plans, and inlet protection measures for
<br /> the work area and downstream areas.
<br /> The TESC measures shall limit the erosion possibility by covering disturbed soils, preventing
<br /> sloughing or raveling of cut and natural slopes, and controlling surface runoff from flowing
<br /> into excavations using measures such as curbs, berms, dikes, rock-lined ditches, and other
<br /> approved measures. Filter fabric fence shall be used to treat small areas of non-concentrated
<br /> runoff prior to discharge from the site.
<br /> Bid Item 10 - Foundation Material, Class A or B
<br /> Measurement and Payment: Unit Price per Ton (TON)
<br /> Watermain Replacement"U" Division B—BID DESCRIPTIONS October 1, 2019