I <br /> CITY OF EVERETT SPECIAL PROVISIONS <br /> 1 1-044 Changes <br /> Delete 1-04.4 and substitute the following: <br /> 1 1-044 Changes <br /> 1-04.4(1) City's Right to Direct Changes to the Work <br /> (******) <br /> The City reserves the right to change the Work at any time. Such changes shall not <br /> invalidate the Contract nor release the Surety, and the Contractor agrees to perform the <br /> Work as changed. Among others, these changes and alterations may include: <br /> 1. Deleting or omitting any part of the Work, Equipment or material to be <br /> provided under this Contract, <br /> 2. Increasing or decreasing quantities, <br /> 3. Altering Specifications, designs, or both, <br /> 4. Altering the way the Work is to be done, <br /> 1 5. Adding new Work or Extra Work, <br /> 6. Altering facilities, Equipment, materials, services, or sites, provided by the <br /> City, and <br /> 1 7. Ordering the Contractor to accelerate or Delay the Work. <br /> If the Contractor and City do not agree upon scope of Work changed or adjustment to <br /> the Contract Sum and Contract Time, the City may, at its sole option, unilaterally direct <br /> the Contractor to implement City directed change by notice. The City shall not pay or <br /> be responsible or liable for changes implemented by the Contractor without explicit <br /> notice from the City to proceed. <br /> 1 1-04.4(2) Extra Work <br /> (******) <br /> At its sole option, the City may (1) perform Extra Work itself, (2) employ others to do it, <br /> (3) direct the Contractor to perform the Extra Work at existing unit Bid price, (4) direct <br /> the Contractor to perform the Extra Work at a mutually agreed upon price, or (5) direct <br /> the Contractor to perform the Extra Work on a Force Account basis. <br /> 1-04.4(3) Change Orders <br /> (******) <br /> Changes to the Work may result in an increase or decrease in Contract Sum, as provided <br /> in 1-09.4 EQUITABLE ADJUSTMENT. Requests for an increase in Contract Time shall <br /> be made as provided in 1-08.3 PROGRESS SCHEDULE as applicable. Substantial <br /> changes in Contract Time, Contract Sum or Work will often be negotiated and agreed <br /> between the Contractor and City before the City directs the Contractor to proceed with <br /> the change. <br /> If the Contractor and City agree on the scope of Work and any changes to Contract Sum <br /> and Contract Time, the Contractor and City shall execute an agreed Change Order. <br /> However, if the Contractor and City do not'agree, the City may, in its sole discretion, <br /> issue a unilateral Change Order in the form attached to the Contract Documents <br /> 1 changing the scope of Work and making any adjustments to the Contract Sum pursuant <br /> to 1-09.4 EQUITABLE ADJUSTMENT and Contract Time pursuant to 1-08.8 <br /> EXTENSIONS OF TIME in such amount and for such time as the City believes <br /> 1 appropriate. Contractor agrees to use the agreed Change Order form attached to the <br /> Contract Documents. The Contractor accepts all requirements, terms and conditions of <br /> a Change Order by: signing it; writing a separate acceptance; or by failing to notify the <br /> I <br /> Watermain Replacement"U" Division 1 —GENERAL REQUIREMENTS October 1, 2019 <br /> WO No—UP3698 SP—55 <br />