Geotechnical Engineering Report <br /> lierracon <br /> Staples Rockery Failure■ Everett,Washington <br /> March 8, 2019 ■ Terracon Project No. 81175122 <br /> the results of previous readings and the rate of construction. As a minimum, readings should be <br /> taken about once a week throughout construction until the wall is completed. All readings should <br /> be reviewed by Terracon. <br /> In order to establish the condition of existing facilities prior to construction, we recommend that <br /> Hilbers, Inc. make a complete inspection and evaluation of pavements, structures, utilities, and <br /> other facilities near the project site. This inspection should be directed towards detecting any <br /> existing signs of damage, particularly those caused by settlement or lateral movement. The <br /> observations should be documented by pictures, notes, survey drawings, or other means of <br /> verification. The contractor should also establish for their own records the existing conditions prior <br /> to construction. <br /> 5.0 GENERAL COMMENTS <br /> Terracon has been retained to prepare the final design plans and specifications for the proposed <br /> soldier pile / tieback retaining wall. These plans and specifications will be prepared using this <br /> geotechnical report as a basis of design and will incorporate considerations from Staples, the <br /> contractor, and the City of Everett. Terracon has also been retained to provide observation and <br /> testing services during soldier pile / tieback retaining wall construction and other earth-related <br /> construction phases of the project. <br /> The analysis and recommendations presented in this report are based upon the data obtained <br /> from the explorations performed at the indicated locations and from other information discussed <br /> in this report. This report does not reflect variations that may occur between explorations, across <br /> the site, or due to the modifying effects of construction or weather. The nature and extent of such <br /> variations may not become evident until during or after construction. If variations appear, we <br /> should be immediately notified so that further evaluation and supplemental recommendations can <br /> be provided. <br /> The scope of services for this project does not include either specifically or by implication any <br /> environmental or biological (e.g., mold, fungi, bacteria) assessment of the site or identification or <br /> prevention of pollutants, hazardous materials or conditions. If the owner is concerned about the <br /> potential for such contamination or pollution, other studies should be undertaken. <br /> This report has been prepared for the exclusive use of Staples, Inc. for specific application to the <br /> project discussed and has been prepared in accordance with generally accepted geotechnical <br /> engineering practices. No warranties, either express or implied,are intended or made. Site safety, <br /> excavation support, and dewatering requirements are the responsibility of others. In the event that <br /> changes in the nature, design, or location of the project as outlined in this report are planned, the <br /> conclusions and recommendations contained in this report shall not be considered valid unless <br /> Terracon reviews the changes and either verifies or modifies the conclusions of this report in <br /> writing. <br /> Responsive ■ Resourceful ■ Reliable 14 <br />