City of Everett 00 7200 - 40 <br /> 2020 Biosolids Removal UT3705-11 <br /> 3. The Contractor knows, or should with the reasonable exercise of ordinary care know, of an <br /> Delay or an event that may cause a Delay; <br /> 4. The Contractor believes,or with the reasonable exercise of ordinary care should believe, it is <br /> entitled to an adjustment of Contract Sum or Time, even if the total or exact amount or impact <br /> cannot yet be determined; <br /> 5. The Contractor believes it is required or directed to perform work that is outside the scope of the <br /> Contract Documents; or <br /> 6. An event occurs, or fails to occur,that the Contractor believes, or should reasonably foresee,may <br /> result in a Contract Claim; <br /> the Contractor shall immediately give Notice to the Owner or Owner's Representative as provided in this <br /> section and elsewhere in the General Conditions and Specifications. 1 <br /> Timely and adequate Notice is a condition precedent to a Contract Claim. <br /> Requests for extensions of Contract Time must be made and will be evaluated in accordance with 5.2.2.2 <br /> Extensions of Contract Time. <br /> Irrespective of any request for additional compensation or Contract Time or any Contract Claim that work <br /> is extra and not part of the original scope of Work,the Contractor shall proceed expeditiously and <br /> promptly with the work as the Owner orders. <br /> If the Contractor fails to follow the procedures of this Contract,including failing to give Notice,the <br /> Contractor completely waives such Contract Claim. In its sole discretion,the Owner may waive strict ' <br /> compliance with procedures,but any such waiver of one or more items or elements does not waive the <br /> necessity for Contractor's strict compliance with any other item or element,nor shall such waiver be <br /> admissible in any legal proceeding for any reason. ' <br /> 10.2 FORM OF NOTICE <br /> The Notice must include the following minimum information: <br /> 1. A complete and accurate description of the event or events giving rise to the Notice, including <br /> dates,times, and locations; <br /> 2. A preliminary list of persons of involved in such event; ' <br /> 3. A statement whether the Contractor believes the event may result in a Contract Claim for <br /> additional Contract Time or adjustment of the Contract Sum; <br /> 4. A date by which Contractor shall begin providing Supplemental Information as provided in this <br /> section. <br /> 10.3 SUPPLEMENTAL INFORMATION ' <br /> Contractor shall supplement the written Notice as soon as possible with a written statement providing the <br /> following: <br /> 1. The date of the event, incident, direction,and other pertinent information; <br /> 2. The nature and circumstances giving rise to the Notice; <br /> 3. The Contract provisions relating to, but not limited to,the event, incident, and direction; ' <br /> 4. The estimated dollar cost, if any,of the Extra Work, or Delay, or both and how that estimate was <br /> determined; and <br /> 5. An analysis of the schedule showing the schedule change or disruption if the Contractor is <br /> asserting a schedule change or disruption. <br /> Throughout any work related to a Notice,the Contractor shall keep complete and accurate records of ' <br /> costs, expenses,and time incurred for which Contractor will or may seek an adjustment. Contractor <br /> 00 7200 - 40 GENERAL CONDITIONS <br />