Laserfiche WebLink
City of Everett 01 2600 - 1 <br /> 2020 Biosolids Removal UT3705-11 <br /> SECTION 01 2600 - CONTRACT MODIFICATION PROCEDURES <br /> 1.1 SUMMARY OF MODIFICATIONS PROCEDURES <br /> A. Changes to the Work may be required due to field conditions, requests made by <br /> the Owner, clarifications to the bid documents, or other needs that result in a <br /> change in the cost of the work and/or change in the number of contract days per <br /> 00 7200-6. The changes to the work will be tracked individually as Request for <br /> Change Proposals (RFCP.). Request for Change Proposals may either be <br /> ' prepared as a Field Directive, or as a request for pricing prior to proceeding with <br /> the work. <br /> ' B. A change order will be issued for one or more RFCP's grouped into a single <br /> change order. Payment for changed work cannot be paid until the change order <br /> is finalized, and approved as outlined per 00 7200-6. <br /> ' C. The Request for Change Proposal shall clearly identify all labor, material, <br /> q g p <br /> equipment, incidentals, including subcontractor's and supplier's invoices or <br /> ' quotes and Contractor's timecards. A reference from the latest approved <br /> schedule shall be attached justifying any time extension request. Mark ups for <br /> all overhead, profit, bond cost, B & 0 taxes, and insurance shall be added per 00 <br /> ' 7200. The form included at the end of this section will be used for directing the <br /> work to be done in one of the two manners described below. <br /> ' D. Contractor, and Subcontractors where required, shall provide a breakdown of <br /> labor costs including basic wage rates, fringe benefits, FICA, FUTA and SUCA <br /> add-ons, per 00 7200. Where premium time is involved, the Contractor shall <br /> provide a breakdown of costs in the same detail. <br /> 1.2 FIELD DIRECTIVE MODIFICATION PROPOSALS <br /> A. Changed conditions and/or unanticipated circumstances may require immediate <br /> ' revisions to Work which are essential and from which a delay would result in a <br /> time and or cost penalty to the project. When such a condition exists, the Owner <br /> shall issue a written Field Directive to the Contractor. <br /> ' B. The Owner will provide direction for the Contractor identifying the necessary <br /> changes to be made. The Field Directive shall be identified with a Request for <br /> ' Change number. The Contractor will provide pricing per 1.01 C of this section <br /> within 15 days of the completion of the work. <br /> 01 2600 - 1 CONTRACT MODIFICATION PROCEDURES <br />