Mr. Scott Connor <br /> SCR Architects <br /> Plan Check Number: B1906-015, First Building Review <br /> June 28, 2019 <br /> Geotechnical <br /> 1. The geotechnical report has been prepared by GeoTest Services, Inc., dated May 3, 2019. The <br /> geotechnical engineer should submit a supplemental report providing additional <br /> recommendations for the foundation system. The recommendations shall state the required soil <br /> criteria for the design of the soil anchors. Additional comments regarding the structural design <br /> are provided below. See Detail 5/F1 and Structural Note 5 on Sheet Fl. See IBC Sections 202, <br /> 1803.2, 1803.5.5, 1803.6, and 1810.1.1. <br /> Architectural <br /> 1. The Project Data section on Sheet A0.01 discusses the proposed portables in the"New Work" <br /> statement. The work describes two new portables, identified as P-10 and P-11, with a total <br /> area of 3,320 SF. However, Sheet A1.01 shows a single portable, identified as P-6/P-7 with an <br /> area of 1,771 SF. Note that the width of the portable is not consistent between Sheets A1.01 <br /> and A2.01. The drawings should be revised as needed for clarity. <br /> 2. The occupant load shall be stated in the Project Data section on Sheet A0.01. See IBC Section <br /> 1004.1 and Table 1004.1.2. <br /> 3. The restroom facilities for the new portable are provided in the existing portable toilet building <br /> shown on Sheet A1.01. It is understood that the building provides a maximum of 3 <br /> waterclosets for each sex. Based on an estimate of the total occupants in the existing and <br /> proposed portable buildings, it appears that additional waterclosets may be required. An <br /> analysis of the restroom facilities shall be submitted verifying that adequate facilities are <br /> provided to accommodate the increased occupancy. See IBC Sections 2902.1 and 2902.3.2 <br /> (WAC). <br /> 4. The new portable building does not include restroom facilities and requires the facilities in an <br /> existing building to meet the requirements of Section 2902.1. The accessible conditions of the <br /> existing portable toilet building are unknown. If the existing building is not fully accessible per <br /> ICC A117.1-09, the existing building shall be upgraded per the requirements of IEBC Section <br /> 705.2. Documentation substantiating the existing conditions, and modifications as needed, <br /> shall be submitted for review. See IBC Sections 1109.2 Exception 7 and 2902.3.1. <br /> 5. Partial Plan 5/A2.02 indicates a ramp on the south side of the upper landing. The following <br /> comments shall be addressed: <br /> a. The plan specifies a ramp slope of 1:8. The ramp appears to be part of the egress route, <br /> and therefore the increased 1:8 slope per IBC Section 1012.2 is not permitted for this <br /> location. The ramp slope shall not exceed 1:12. The ramp shall be revised. See IBC <br /> Section 1101.2 and ICC A117.1-09 Section 405.2. <br /> b. The plan shall specify that the ramp be provided with a slip-resistant surface. See IBC <br /> Section 1012.7.1. <br /> (--,-~m <br /> 3200 Cedar Street 0425.257.8810 0 everetteps@everettwa.gov <br /> Everett,WA 98201 425.257.8857 fax everettwa.gov/permits <br /> Page 2 - <br />