10.4.3 The name of each person employed or associated with Design-Builder, Subcontractors, <br /> suppliers, and/or the Owner with knowledge about the event or condition which gave rise to the <br /> Claim; <br /> 10.4.4 Copies of documents and a written description of the substance of any oral <br /> communications that concern or relate to the Claim; <br /> 10.4.5 The specific provisions of the Contract Documents on which the Claim is based; <br /> 10.4.6 if an adjustment in the Contract Price is sought, the exact amount sought, calculated in <br /> accordance with the Contract Document and accompanied by all records supporting the Claim; <br /> 10.4.7 If an adjustment in the Contract Time is sought,the specific days and dates for which it is <br /> sought; the specific reason Design-Builder believes an adjustment in the Contract Time should be <br /> granted;and Design-Builder's analyses of its construction schedule, any specific schedule analysis <br /> as required by the Contract Documents, and all updates to demonstrate the reason for the <br /> adjustment in Contract Time; and, <br /> 10.4.8 A statement certifying, under penalty of perjury, that after the exercise or reasonable <br /> diligence and investigation the Claim is made in good faith, that the supporting cost and pricing <br /> data are true and accurate to the best of the Design-Builder's knowledge and belief, that the Claim <br /> is fully supported by the accompanying data,and that the amount requested accurately reflects the <br /> adjustment in the Contract Price or Contract Time for which Design-Builder believes the Owner is <br /> liable. <br /> 10.5 Cooperation/Claims Audit. Design-Builder shall cooperate with Owner or its designee in the <br /> evaluation of its Claim and provide all information and documentation requested by Owner or its <br /> designee. Claims filed against Owner shall be subject to audit at any time following the filing of the <br /> Claim. Failure of Design-Builder, or Subcontractors of any tier, to maintain and retain reasonably <br /> sufficient records to allow Owner to verify all or a portion of the Claim or to permit Owner access to <br /> the books and records of Design-Builder, or Subcontractors of any tier, shall constitute a waiver of <br /> that part of the Claim and shall bar any recovery on that part of the Claim. <br /> 10.6 Owner Evaluation of Claim. After Design-Builder has submitted a fully documented Claim that <br /> complies with Article 10, Owner shall respond, in writing,to Design-Builder within 60 days from the <br /> date the fully documented Claim is received with a decision regarding the Claim. The Claim shall <br /> be deemed denied upon the 61st day following receipt of the Claim by Owner. Any Claims not fully <br /> resolved must be submitted to Dispute Resolution in accordance with Section 10.7. <br /> 10.7 Dispute Avoidance and Resolution <br /> 10.7.1 The parties are fully committed to working with each other throughout the Project and agree <br /> to communicate regularly with each other at all times so as to avoid or minimize disputes or <br /> disagreements. If disputes or disagreements do arise, Design-Builder and Owner each commit to <br /> resolving such disputes or disagreements in an amicable, professional and expeditious manner so <br /> as to avoid unnecessary losses, delays and disruptions to the Work. <br /> 10.7.2 If a Claim or other disagreement cannot be resolved through Design-Builder's <br /> Representative and Owner's Representative, then Design-Builder's Senior Representative and <br /> Owner's Senior Representative, upon the request of either party, shall meet as soon as <br /> conveniently possible, but in no case later than 30 days after such a request is made,to attempt to <br /> resolve such Claim. <br /> 10.7.3 If after meeting the Senior Representatives determine that the Claim or other disagreement <br /> cannot be resolved on terms satisfactory to both parties, the parties shall submit within 30 days <br /> after the conclusion of the meeting of Senior Representatives, or within a mutually agreed on time <br /> frame, the dispute or disagreement to non-binding mediation. The mediation shall be conducted <br /> by a mutually agreeable impartial mediator,or if the parties cannot so agree,a mediator designated <br /> East Clearwell Project General Conditions of Contract Page 21 <br />