Change Order Cover Sheet/For Internal City Use Only <br /> 3 <br /> CONTRACT TIME <br /> Original Contract Duration I Working Days ❑ Calendar Days ® 21 <br /> Date of Notice to Proceed 11-8-2019 <br /> Cumulative adjustment to duration by prior Change Orders 0 <br /> Adjustment to duration by this Change Order <br /> New Contract Duration (including this Change Order) 0 <br /> EXPLANATION/JUSTIFICATION <br /> The change order is the result of modified quantities of contaminated soils discovered <br /> during the construction phase. Additionally, the sump pump was filled with water mixed with <br /> traces of contaminates which resulted in the need to dispose of the discovered material. <br /> CityStaff Contact: <br /> Date <br /> 19 <br />