Storm water Pollution Prevention Plan <br /> 4.0 Construction Phasing and BMP <br /> Implementation <br /> The BMP implementation schedule will be driven by the construction schedule. The following <br /> provides a sequential list of the proposed construction schedule milestones and the <br /> corresponding BMP implementation schedule. The list contains key milestones such as wet <br /> season construction. <br /> The BMP implementation schedule listed below is keyed to proposed phases of the construction <br /> project, and reflects differences in BMP installations and inspections that relate to wet season <br /> construction. The project site is located west of the Cascade Mountain Crest. As such, the dry <br /> season is considered to be from May 1 to September 30 and the wet season is considered to be <br /> from October 1 to April 30. <br /> • Estimate of Construction start date: May 2016 <br /> • Estimate of Construction finish date: November 2016 <br /> • Mobilize equipment on site: <br /> • Mobilize and store all ESC and soil stabilization products <br /> (store materials on hand BMP C150): <br /> • Install ESC measures: <br /> • Install stabilized construction entrance: <br /> • Begin clearing and grubbing: <br /> • Temporary erosion control measures (hydroseeding): <br /> • Site inspections reduced to monthly: <br /> • Begin concrete pour and implement BMP C151: <br /> • Excavate and install new utilities and services (Phase 1): <br /> • Complete utility construction: <br /> • Begin implementing soil stabilization and sediment <br /> control BMPs throughout the site in preparation for wet <br /> season: <br /> • WET SEASON STARTS: October 1, 2016 <br /> 21 17576.003.doc <br />