Laserfiche WebLink
CITY OF EVERETT SPECIAL PROVISIONS [Modified per Addendum #1] <br /> 1-04.6 Variation in Estimated Quantities <br /> Revise the first paragraph to read as follows: <br /> Payment to the Contractor will be made only for the actual quantities of Work <br /> performed and accepted in conformance with the Contract. When the accepted <br /> quantity of Work performed under a unit item varies from the original Proposal quantity, <br /> payment will be at the unit Contract price for all Work unless the total accepted <br /> quantity of any Contract item, adjusted to exclude added or deleted amounts included <br /> in change orders accepted by both parties, increases or decreases by more than 25 <br /> percent from the original Proposal quantity, and if the total extended bid price for that <br /> item at time of award is equal to or greater than 10 percent of the total contract price at <br /> time of award. In that case, payment for contract work may be adjusted as described in <br /> the Standard Specifications and modified in these Special Provisions. <br /> 1-04.7 Differing Site Conditions (Changed Conditions) <br /> Delete all of 1-04.7 and substitute the following: <br /> Upon discovery and before such conditions are disturbed, the Contractor shall <br /> promptly provide Notice to the City's Representative of: <br /> Pre-existing subsurface or latent physical conditions at the site differing materially ' <br /> from those indicated in this Contract, or <br /> Pre-existing unknown physical conditions at the site, of an unusual nature, <br /> differing materially from those ordinarily encountered and generally recognized as <br /> inhering in work of the character provided for in this Contract. <br /> Upon written request, the City's Representative shall determine whether the <br /> actual conditions encountered by the Contractor conditions are materially , <br /> different and, if so, are the cause of a material increase or decrease in the <br /> Contractor's cost of performance of the Work, or extend the duration of the <br /> critical path of the schedule. Upon such determination, the City's <br /> Representative will make an adjustment of Contract Sum or Contract Time, as <br /> appropriate. Extensions of Contract Time will be evaluated in accordance with <br /> 1-08.3 PROGRESS SCHEDULE[Added per Addendum 1].. <br /> The City's Representative's determination that differing site conditions do not <br /> exist and/or the appropriate adjustment in Contract Sum or Contract Time (if <br /> any) shall be final[Revlsed per Addendum 1]. If there is a decrease in the cost or time <br /> required to perform the Work, failure of the Contractor to notify the City's <br /> Representative of the differing site condition shall not affect the City's right to make an <br /> adjustment in the Contract Sum or Contract Time. Additionally, no Contract Claim or <br /> adjustment of Contract Sum or Contract Time shall be allowed unless the Contractor <br /> has followed the procedures provided for in this Contract, including, but not limited to, <br /> furnishing timely Notice of the event and its effect on Contract Time and Contract Sum <br /> as required herein. <br /> Contractor shall in no event be entitled to a Contract Claim or adjustment of <br /> Contract Sum or Contract Time based on an allegation that the pre-existing <br /> subsurface or latent physical conditions at the site differing materially from <br /> those indicated in this Contract unless Contractor establishes that it reasonably <br /> relied on the conditions indicated in this Contract when making its bid, that the <br /> actual conditions encountered on the site differed materially from those ' <br /> indicated in this Contract, and that such materially-different conditions were not <br /> foreseeable at the time of its bidIAdded per Addendum 1]. <br /> Sewer 0 Division 1 —GENERAL REQUIREMENTS Addendum No. 1 <br /> WO No—UP3691 SP—64 May 2020 <br />