I <br /> CITY OF EVERETT SPECIAL PROVISIONS [Modified per Addendum #1] <br /> the approved partial payment estimate, less retainage and any amounts the City may <br /> withhold pursuant to Contract or law. The recommendation of the City's <br /> Representative is not conclusive, final or binding upon the City. <br /> In the event the City's Representative does not concur with the estimate, the <br /> Contractor may make the changes necessary to obtain the City's Representative's <br /> concurrence and resubmit the partial payment estimate, or submit the original progress <br /> payment estimate directly to the City, indicating in writing its reasons for refusing to <br /> make the changes necessary to obtain concurrence. <br /> 1-09.9(3) Withholding Payment <br /> The City's Representative may refuse to recommend the whole or any part of any <br /> payment if in the City's Representative's opinion it would be incorrect to make such <br /> recommendation to the City. The City's Representative may also refuse to recommend <br /> any such payment, or because of subsequently discovered evidence or the result of <br /> tests, may nullify any such payment previously recommended to such extent as may <br /> be necessary in the City's Representative's opinion to protect the City from loss as a <br /> result of: <br /> 1. Defective or damaged Work. <br /> 2. A deductive Change Order. <br /> 3. Persistent failure of the Contractor to perform the Work in accordance with <br /> the Contract Documents, including failure to maintain the progress of the <br /> Work in accordance with the construction schedule. Persistent failure to <br /> maintain the progress of the Work shall mean that for a period of two <br /> consecutive months following a written notice from the City's Representative <br /> or City, the Contractor fails to correct a behind-schedule condition at a rate <br /> that would reasonably indicate that it will finish the Project on schedule. <br /> 4. Disregard of authority of the City or City's Representative or the laws of any <br /> public body having jurisdiction. <br /> 5. Liquidated damages. <br /> ' 6. Misrepresentation of the quality of materials or Equipment installed or amount <br /> of Work performed. <br /> 7. Discovery that a previous pay estimate erred with respect to the amount of <br /> Work performed or Equipment or materials installed, irrespective of the City's <br /> Representative's recommendation at the time of the progress pay estimate. <br /> The City may refuse to make payment of the full amount recommended by the City's <br /> Representative because of Contract Claims made against the City on account of <br /> Contractor's performance or furnishing the Work or because of liens filed in connection <br /> with the Work or other set offs entitling City to reduce the amount recommended. In <br /> ' such case, the City shall give Contractor prompt written notice with copy to the City's <br /> Representative stating the reasons for each action. <br /> 1-09.9(4) Final Payment Procedure <br /> ' Upon receipt of Contractor's written Notice that the Work is ready for final inspection <br /> and acceptance and upon receipt of a Final Contract Voucher Certification, the City's <br /> Representative will inspect the Work. If the City's Representative finds the Work <br /> acceptable under the Contract Documents and the Contract fully performed and if the <br /> Contractor has signed a Final Contract Voucher Certification, the City's Representative <br /> will issue a final Certificate for Payment. The Certificate for Payment will state that to <br /> the best of the City's Representative's knowledge, information and belief, the Work <br /> appears to have been completed in accordance with terms and conditions of the <br /> Sewer 0 Division 1 -GENERAL REQUIREMENTS Addendum No. 1 <br /> WO No-UP3691 SP-123 May 2020 <br />