Laserfiche WebLink
1 schedule may be a critical path method (CPM) schedule, bar chart, or other standard I <br /> 2 schedule format. Regardless of which format used, the schedule shall identify the critical <br /> 3 path. The Engineer will evaluate the Type A Progress Schedule and approve or return the III <br /> 4 schedule for corrections within 15 calendar days of receiving the submittal. <br /> 5 <br /> 6 COE 1-08.4.DOCX <br /> 7 1-08.4 Prosecution of Work <br /> 8 <br /> 9 Delete this section and replace it with the following: <br /> 10 <br /> 11 1-08.4 Notice to Proceed and Prosecution of Work <br /> 12 (City of Everett) <br /> 13 <br /> 14 Notice to Proceed will be given after the contract has been executed and the contract <br /> 15 bond and evidence of insurance have been approved and filed by the Contracting <br /> 16 Agency. The Contractor shall not commence with the work until the Notice to Proceed <br /> 17 has been given by the Engineer. The Contractor shall commence construction activities <br /> 18 on the project site within ten days of the Notice to Proceed Date, unless otherwise <br /> 19 approved in writing. The Contractor shall diligently pursue the work to the physical <br /> 20 completion date within the time specified in the contract. <br /> 21 <br /> 22 When shown in the Plans, the first order of work shall be the installation of high visibility111 <br /> 23 fencing to delineate all areas for protection or restoration, as described in the Contract. <br /> 24 Installation of high visibility fencing adjacent to the roadway shall occur after the <br /> 25 placement of all necessary signs and traffic control devices in accordance with 1-10.1(2). I <br /> 26 Upon construction of the fencing, the Contractor shall request the Engineer to inspect the <br /> 27 fence. No other work shall be performed on the site until the Contracting Agency has <br /> 28 accepted the installation of high visibility fencing, as described in the Contract. <br /> 29 <br /> 30 1-08.4.INST2.GR1 <br /> 31 The last sentence of Section 1-08.4 is revised to read: <br /> 32 <br /> 33 1-08.4.OPT4.GR1 <br /> 34 (April 6, 2020) <br /> 35 No other work shall be performed on the site until the Contracting Agency has accepted I <br /> 36 the installation of high visibility fencing, as described in the Contract, and a COVID-19 <br /> 37 Health and Safety Plan (CHSP) has been prepared in accordance with Section 1-07.4(2) <br /> 38 as supplemented in these specifications, COVID-19 Health and Safety Plan (CHSP). <br /> 39 <br /> 40 1-08.5.GR1 <br /> 41 Time for Completion <br /> 42 <br /> 43 1-08.5.I NST2.GR1 <br /> 44 Section 1-08.5 is supplemented with the following: <br /> 45 <br /> 46 1-08.5.O PT7.F R 1.DO CX <br /> 47 (March 13, 1995) <br /> 48 This project shall be physically completed within *** 100 *** working days. <br /> 49 <br /> I <br /> MAPLE HEIGHTS BRIDGE SEISMIC RETROFIT PAGE 64 OF 106 SPECIAL PROVISIONS—Addendum 1 <br /> WORK ORDER#3693 MAY 4,2020 FEDERAL AID#BHM-2776(008) <br />