CO # 25 COSTS
<br /> Bid Item or New Item Cost Cost by Schedule Cost
<br /> Schedule A Schedule B Schedule C
<br /> A-43 $44,850.00 $44,850.00
<br /> A-77 $52,000.00 $52,000.00
<br /> A-92 $65,700.00 $65,700.00
<br /> A-171 $35,000.00 $35,000.00
<br /> A-326 $1,020.00 $1,020.00
<br /> A-327 $5,545.00 $5,545.00
<br /> A-328 $6,330.00 $6,330.00
<br /> A-329 $11,299.05 $11,299.05
<br /> A-330 $20,767.05 $20,767.05
<br /> A-331 $90,698.20 $90,698.20
<br /> A-332 $4,765.00 $4,765.00
<br /> B-113 $7,456.00 $7,456.00
<br /> B-114 $27,746.00 $27,746.00
<br /> B-115 $4,750.00 $4,750.00
<br /> B-116 $6,975.00 $6,975.00
<br /> B-117 $11,148.00 $11,148.00
<br /> B-118 $8,520.81 $8,520.81
<br /> B-119 $106,177.50 $106,177.50
<br /> B-120 $1,493.00 $1,493.00
<br /> B-121 $7,838.00 $7,838.00
<br /> C-105 $39,937.00 $39,937.00
<br /> TOTAL COST $560,015.61 $337,974.30 $182,104.31 $39,937.00
<br /> Original Contract Price $13,789,438.50
<br /> Total CO Costs to Date $648,879.23
<br /> Total Contract Costs to Date $14,438,317.73
<br /> Amount of CO#25 $560,015.61
<br /> Total CO Costs After CO 25 $1,208,894.84
<br /> Total Contract Value to Date $14,998,333.34