Project: Grand Avenue Park Bridge <br /> Change Order No.: 25 <br /> Change Order Effective Date: 9-29-2020 <br /> New Item # C-105—Elevator Changes. Following the elevator inspection by Washington State <br /> Labor and Industries, Elevator Division (L&I)there were additional changes required by the L&I <br /> Inspector that were not shown on the approved drawings. Revisions included electrical work, <br /> rerouting of the HVAC lines within the elevator shaft that were required to be relocated outside of the <br /> shaft, and concrete core drilling to reroute the HVAC lines. The previous work was installed per plan <br /> and these changes are additional work. This new item is being added to account for these additional <br /> costs. Working Days impacted: 7. <br /> Exhibit C—Additional Contract Time: <br /> There are 29 additional working days added to this Change Order#25. <br /> Page 8 of 8 <br />