CITY OF EVERETT SPECIAL PROVISIONS <br /> 1-09.11ARemedies <br /> (******) <br /> 1-09.11A(1) General <br /> If a Contract Claim has merit in whole or in part, then Contractor's sole remedies shall <br /> be those provided in this subsection. Contractor shall timely and strictly comply with the <br /> requirements of 1-04.5 NOTICE BY THE CONTRACTOR and 1-09.11(2) CONTRACT <br /> CLAIMS and all other Contract Documents relating to the Contract Claim. Adjustments <br /> to Contract Time shall be determined pursuant to 1-08.3 PROGRESS SCHEDULE and <br /> 1-08.8 EXTENSIONS OF TIME. Failure to comply strictly and timely shall be deemed <br /> a waiver of the Contract Claim. <br /> 1-09.11 A(2) Extra Work <br /> 1-09.11A(2)A Adjustment of Contract Sum <br /> If the Contractor is entitled to an adjustment of Contract Sum because of Extra <br /> Work, the adjustment shall be calculated and paid as provided in 1-09.4 <br /> EQUITABLE ADJUSTMENT. This amount includes jobsite and home office <br /> Overheads for such Work, including any schedule delays relating to such Work. <br /> Therefore, no compensation in addition to that provided in 1-09.6 FORCE <br /> ACCOUNT shall be paid for such thing as Extended Overhead or other costs or <br /> damages. <br /> 1-09.11A(2)B Extension of Contract Time <br /> Extensions of Contract Time caused by Extra Work shall be determined as provided <br /> in 1-08.3 PROGRESS SCHEDULE and 1-08.8 EXTENSIONS OF TIME. <br /> 1-09.11 A(3) Delays <br /> 1-09.11A(3)A City Caused Delay Unrelated to Extra Work <br /> 1-09.11A(3)A1 Adjustment of Contract Sum <br /> If the Contractor is entitled to an adjustment of Contract Sum because of a <br /> Delay solely caused by the City that does not relate to Extra Work, Contractor <br /> shall only be compensated for the items below, less all funds paid pursuant to <br /> any change in the Contract Sum that contributed to the Delay: <br /> 1. Documented, incurred cost of nonproductive field supervision or <br /> labor extended because of the delay; <br /> 2. Documented, incurred cost of home office supervision to attend <br /> jobsite meetings; <br /> 3. Documented, incurred cost of temporary facilities or equipment <br /> rental extended because of the Delay; <br /> 4. Documented, incurred cost of insurance extended because of the <br /> Delay; <br /> 5. General and administrative overhead in an amount to be agreed <br /> upon, but not to exceed three percent of original Contract Sum <br /> divided by the Contract Time for each day of the Delay. <br /> City shall not owe Contractor compensation for Extended Overhead or other <br /> delay costs to the extent Contractor or anyone other than the City contributed <br /> to or is concurrently responsible for the Delay. <br /> 1-09.11A(3)A2 Adjustment of Contract Time <br /> If the Contractor is entitled to an adjustment of Contract Time because of a <br /> Delay solely caused by the City that does not relate to Extra Work, Contractor <br /> Jackson Park Area Stormwater Separation <br /> WO No—UP3703 Division 1 —GENERAL REQUIREMENTS September 2020 <br /> SP-121 <br />