CITY OF EVERETT SPECIAL PROVISIONS <br /> shall be entitled to an adjustment of Contract Time to the extent the Delay <br /> increases the duration of the Project, as measured by the critical path and as <br /> demonstrated pursuant to the requirements of 1-08.8 EXTENSIONS OF TIME. <br /> 1-09.11A(3)B Contractor Caused Delay <br /> If the Contractor is solely responsible for any Delay to any interim milestone, <br /> Substantial Completion, Physical Completion, or the Completion Date, the City shall <br /> be entitled to liquidated or other damages as provided elsewhere in the Contract <br /> Documents. The Contractor accepts the risk of any Delays caused by strikes, work <br /> slowdowns,job actions and labor unrest of any kind. Contractor shall not be entitled <br /> to any increase in Contract Sum or Contract Time due to a Delay it caused. <br /> 1-09.11A(3)C Delays Concurrently Caused by Contractor and Owner <br /> If the City and the Contractor cause a Delay concurrently, neither the City nor the <br /> Contractor shall be liable to the other except as provided herein. <br /> 1-09.11A(3)C1 Adjustment of Contract Sum <br /> The Contractor shall not be entitled to any adjustment in Contract Sum for <br /> Delays concurrently caused by the City and the Contractor. <br /> 1-09.11A(3)C2 Adjustment of Contract Time <br /> The Contractor shall be entitled to an extension of Contract Time for the City <br /> caused portion of any Delay concurrently caused by the City and Contractor to <br /> the extent the City caused the Delay to extend longer than if the Contractor had <br /> solely caused the Delay. <br /> 1-09.11A(3)D Third Party Caused Delays and Force Majeure <br /> For the purposes of this section 1-09.11A(3)D, a "Force Majeure Event" is <br /> defined as earthquake, flood, pandemic (and governmental laws, regulations, <br /> requirements, and orders resulting therefrom), natural disasters, acts of war <br /> or acts of terrorism. Pandemic in the preceding sentence includes without <br /> limitation the COVID-19 / novel coronavirus (SARS-CoV-2) pandemic, which <br /> is the subject of the Governor's proclamation dated February 29, 2020, and <br /> subsequent proclamations. <br /> For the purposes of this section 1-09.11A(3)D, a "Third Party" is defined as a <br /> third party for whom neither the Contractor nor the City is responsible. <br /> 1-09.11A(3)D1 Adjustment of Contract Sum <br /> The City and the Contractor shall not be responsible to compensate each <br /> other financially for any Delay to the extent caused by a Third Party or a <br /> Force Majeure Event. A Delay caused by a utility's failure to provide <br /> service or relocate its lines (despite a timely request for such service or <br /> relocation) is an example of this kind of Delay for which neither the <br /> Contractor nor the City is financially responsible to the other. Mis-located <br /> utility lines or utility lines not located are another example of a Delay for <br /> which neither the Contractor nor the City is responsible to the other. <br /> However, the Contractor's failure to request a utility locate or relocation in <br /> a timely way is not, and any resulting Delay would be the responsibility of <br /> the Contractor. Because the Contractor is responsible for ordering <br /> materials and Equipment, Contractor shall not be entitled to an <br /> adjustment of Contract Time or Contract Sum due to Delays caused by <br /> the lack of materials or Equipment. A strike, job action, slowdown, work <br /> to rule, or other job action or labor dispute or problem is not a Delay <br /> caused by a Third Party. <br /> Jackson Park Area Stormwater Separation <br /> WO No—UP3703 Division 1 —GENERAL REQUIREMENTS September 2020 <br /> SP-122 <br />