Laserfiche WebLink
CITY OF EVERETT SPECIAL PROVISIONS <br /> Plan to meet the Contractor's schedule and method of construction. The <br /> Contractor shall develop a schedule for implementation of the TESC work and <br /> incorporate it into the Contractor's progress schedule. <br /> At the request of the Engineer updated TESC Plans shall be prepared and <br /> provided to the City. <br /> 8-01.3(1)B Erosion and Sediment Control (ESC) Lead <br /> Revise the second and third paragraphs in 8-01.3(1)B to read as follows: <br /> The ESC Lead shall implement the TESC Plan. Implementation shall include, <br /> but is not limited to: <br /> 1. Installing and maintaining all temporary erosion and sediment control <br /> Best Management Practices (BMPs) included in the TESC Plan to <br /> assure continued performance of their intended function. Damaged or <br /> inadequate TESC BMP's shall be corrected immediately. <br /> 2. Updating the TESC Plan to reflect current field conditions. <br /> The ESC Lead shall also inspect all areas disturbed by construction activities, <br /> all on-site erosion and sediment control BMP's, and all stormwater discharge <br /> points at least once every calendar week and within 24-hours of runoff events <br /> in which stormwater discharges from the site. Inspections of temporarily <br /> stabilized, inactive sites may be reduced to once every calendar month. <br /> Delete paragraph two of 8-01.3(1)A <br /> 8-01.3(2) Seeding, Fertilizing, and Mulching <br /> 8-01.3(2)A Preparation For Application <br /> 8-01.3(2)A1 Seeding <br /> Revise the third sentence in the first paragraph in 8-01.3(2)A1 to read as follows: <br /> Cultivate seeding restoration areas no sooner than one week prior to seeding. <br /> Supplement 8-01.3(2)A1 by adding the following: <br /> All areas to be seeded shall be raked or similarly treated so as to provide a <br /> smooth, consistent, friable surface, acceptable for seeding as determined by <br /> the Engineer. <br /> All areas to be seeded shall be free of all visible clods, rocks and debris <br /> measuring one-inch or larger in any dimension. Any exposed tree roots in cut <br /> slopes shall be cut neatly and protected. <br /> 8-01.3(2)B Seeding and Fertilizing <br /> Supplement 8-01.3(2)B by adding the following: <br /> Provide topsoil testing and amendments in accordance with section 9-14.1(4) <br /> of the Special Provisions. <br /> Use hydroseeding application method where feasible, uniformly apply a slurry <br /> of seed, fertilizer, mulch and water over all disturbed areas unless restoring <br /> with sod or shown otherwise on the Plans. <br /> Use Seed Mix#1, as specified in 9-14.2 of these Special Provisions in restoring <br /> areas not having established lawns. <br /> Apply permanent seed mixture #1 uniformly over the areas being restored at a <br /> rate of 4-pounds per 1,000 square feet. <br /> Apply temporary seed mixture uniformly over the areas being restored at a rate <br /> of 2-pounds per 1,000 square feet. <br /> Jackson Park Area Stormwater Separation September 2020 <br /> WO No. - UP3703 Division 8—MISC CONSTRUCTION <br /> SP—166 <br />