CITY OF EVERETT SPECIAL PROVISIONS <br /> 1-05.14 Cooperation With Other Contractors <br /> Delete all of 1-05.14 and substitute the following: <br /> Nothing in the Contract shall be interpreted as granting to the Contractor exclusive <br /> occupancy of the Project area. The Contractor shall ascertain to its own satisfaction the <br /> scope of the Project and the nature of any other contracts that have been or may be <br /> awarded by the City in the construction of the Project, or to the end that the Contractor <br /> may perform this Contract in the light of such other contracts, if any. <br /> The Contractor shall not cause unnecessary hindrance or Delay to others working on <br /> this or other projects. If the performance of a contract for the Project is likely to be <br /> interfered with by the simultaneous performance of some other contract or contracts, the <br /> Engineer will decide which Contractor shall cease Work temporarily and which <br /> Contractor shall continue, or whether the Work under the contracts can be coordinated <br /> so that the contractors mayproceed simultaneously. On all y questions concerning <br /> conflicting interest of contractors performing related Work, the decision of the Engineer <br /> shall be binding upon all contractors concerned and the City, the Engineer, the City's <br /> Representative, and their consultants shall not be responsible for any damages suffered <br /> or extra costs incurred by the Contractor resulting directly or indirectly from the Award or <br /> performance or attempted performance of any other contract or contracts on the Project <br /> or caused by a decision or omission of the Engineer respecting the order of precedence <br /> in the performance of the contracts. <br /> If, through acts of neglect on the part of the Contractor, any others suffer loss or damage <br /> on the Work, the Contractor agrees to resolve such loss or damage fairly and <br /> expeditiously. If such other shall assert any claim against the City, the Engineer, the <br /> City's Representative, or their consultants on account of any damage alleged to have <br /> been so sustained, the City shall notify the Contractor, who shall hold harmless, <br /> indemnify, and defend the City, Engineer, the City's Representative, and their <br /> consultants, and each of their directors, officers, employees, and agents against any <br /> such claim, including all attorney's fees and any other costs incurred by the indemnified <br /> parties relative to any such claim. <br /> The Contractor shall coordinate its work with other contractors and utility companies that <br /> may have facilities in the Project area and cooperate with them. He shall also coordinate <br /> its activities with the City; and no water mains, individual water services, street, or private <br /> driveways may be closed off without a minimum of five working days notice to the City <br /> and the private property owner. Should the property owner or the City have adequate <br /> reason, as determined by the Engineer, to avoid access or water service shutoff at the <br /> scheduled time, the Contractor shall reschedule its work to meet the new condition. <br /> Final grading to subgrade and subgrade preparation in those areas disturbed by the <br /> utilities companies shall be the responsibility of the Contractor and included in the street <br /> construction and no additional compensation will be paid. <br /> The Contractor shall cooperate with the utility companies and their subcontractors and <br /> so conduct its operations that the necessary construction of their facilities can be <br /> accomplished to the mutual satisfaction of the City of Everett and the utility companies. <br /> Jackson Park Area Stormwater Separation <br /> WO No—UP3703 Division 1 —GENERAL REQUIREMENTS September 2020 <br /> SP-68 <br />