Project Everett Downtown Streetscape Improvement <br />Change Order No.4 <br />Change Order Effective Date December 9, 2020 <br />New Item # C-210 — Hydroblaster Roadway Preparation. Following the placement of concrete <br />panels, a sealant was applied to the concrete road surface for protection and curing. For pavement <br />markings to be applied to the roadway, the sealant needed to be removed or scarified, for liquid cold <br />applied pavement markings to properly stick to the new concrete pavement This new item is being <br />created to account for costs to perfolin the roadway prep work using a hydroblaster machine. <br />New Item # D-10 & E-25 — Equitable Adjustment for Differing Site Conditions. During roadway <br />excavation on Rucker, multiple layers of concrete, along with asphalt, sand, and brick were <br />encountered, which were not shown in the Contract documents and were unexpected. These new items <br />are being created to account for additional costs for disposal of mixed loads New Item # E-25 <br />specifically allocates a portion of the Equitable Adjustment for Differing Site Conditions costs into <br />schedule E, onto the Utility Department since the waterline was excavated thru the same area on <br />Rucker, from Everett Avenue to Pacific Avenue where the differing site conditions occurred. <br />New Item # E-26 — Roadway Excavation Including Haul. New item E-26 accounts for additional <br />roadway excavation in the watermain trench on Rucker Avenue. This new item R-26 is being added to <br />schedule E to allocate the Utility division portion of additional costs for roadway excavation including <br />haul as a result of the differing site conditions encountered on the project. <br />New Item # E-27 — Crushed Surfacing Base Course (CSBC) Bid Item # D-5 exceeded plan <br />quantity, and it was modified to account for additional costs. This additional new item E-27 is being <br />added to schedule E to allocate the Utility division portion of additional costs for additional CSBC <br />material within the waterline trench area on Rucker Avenue, from Everett Avenue to Pacific Avenue <br />New Item # E-28 — Gravel Borrow Including Haul. Gravel Borrow placement on Rucker Avenue <br />exceeded plan quantity, including the area within the waterline work. This new item E-28 is being <br />added to schedule E to allocate the Utility division portion of additional costs for additional Gravel <br />Borrow material within the waterline trench area on Rucker Avenue, from Everett Avenue to Pacific <br />Avenue <br />New Item # E-29 — Water Meter Box. This item was originally listed in Schedule C but should have <br />been in the Water Schedule E This item is being added to Schedule E to account for costs to install <br />new water meter boxes as part of the new watennain and appurtenances on Rucker Avenue. <br />New Item # E-30 - Math Error Correction in Change Order #1. This new item corrects an addition <br />error shown on page 7 of change order #1, which showed costs being added under schedule E of <br />$50,850.32 and should have been $37,950.00, resulting in an over payment of $50,850.32 - $37,950.00 <br />_ $12,900.32. <br />New Item # F-1 Covid-19 Worker Protection. The Contractor submitted a cost impact price as a <br />result of Covid-19 in the amount of $245,914.49. The parties have agreed to a cost reimbursement for <br />Covid-19 Worker Protection of $48,754 50 for handwashing stations, cleaning and sanitation <br />materials, personal protective equipment, and worker screening stations The agreed to reimbursement <br />includes no contractor markup. <br />Page 6 of 8 <br />