1 <br /> Revised 2021-01-19— <br /> Addendum No. 1 <br /> 5.2. CONTRACT TIME <br /> 5.2.1. General I <br /> TIME IS OF THE ESSENCE IN PERFORMING THE CONTRACT. Failure to complete the <br /> Project within the contractually specified time may affect other Projects and Owner activities. Contract <br /> Time starts upon the later of the issuance of the Notice to Proceed or a date specified in the Notice to <br /> Proceed. The Contractor shall promptly start the Work as soon as possible after the date of the Notice to <br /> Proceed and shall prosecute the Work so that the various portions of the Project shall be completed in <br /> accordance with the Contract Time period. Contractor shall perform its work at such times and in such <br /> ways that the Work is not damaged by weather such as wind,rain,or snow. Contractor shall correct or <br /> repair at its sole expense any Work damaged by weather, irrespective of whether such damage is covered <br /> by insurance. No portions of the Work where acceptable quality will be affected shall be constructed <br /> 111 <br /> while unfavorable conditions exist. By bidding on the Project and executing a Contract to perform the <br /> Work, Contractor agrees the contractually required completion dates are feasible,reasonable,and <br /> achievable for the Contract Sum. Contractor represents that it has considered all factors relevant to its <br /> price and achieving the Completion Dates, including,but not limited to,weather, Site access, labor <br /> conditions and the availability of materials, supplies and Equipment. Compliance with 10.NOTICE TO <br /> OWNER, 12. CONTRACT CLAIMS, and 5.2.2. Construction Schedule are conditions precedent to a <br /> request for, consideration of, and grant of,any extension of Contract Time. Failure to request a time <br /> extension in the manner and in the time required by this section,and the Specifications referred to herein, <br /> constitutes a waiver by the Contractor of any and all entitlement to an extension of time and any <br /> adjustment of Contract Sum arising out,or related to, such Delay. I <br /> 5.2.2. Construction Schedule <br /> 5.2.2.1 General <br /> Contractor shall submit,update and maintain schedules as required by the Contract Documents. <br /> The Contractor shall provide sufficient material,equipment, and labor to meet the interim milestones, <br /> Substantial Completion,Physical Completion and Completion Dates provided by the Contract <br /> Documents. The Owner allocates its resources to a Contract based on the total time allowed in the <br /> Contract. The Contractor may submit a schedule indicating Completion Date earlier than the end of <br /> Contract Time,but Owner cannot guarantee its resources will be available to meet such schedule. Owner <br /> shall not pay or be liable for any additional compensation if the Contractor is not able to meet a schedule <br /> that indicates a Completion Date earlier than the end of Contract Time. <br /> Failure to schedule Owner furnished or installed materials and Equipment for installation on or after its <br /> planned arrival pursuant to the Owner's contract with the supplier or failure to Notify the Owner of tasks <br /> dependent upon the fact or date of arrival of such Owner furnished materials and Equipment, constitute a <br /> waiver by Contractor of any Contract Claim arising out of or related to the timeliness of the furnishing or <br /> installation of such material and Equipment. All schedules must allow for timely incorporation of any <br /> other's work under separate contract with Owner and for timely incorporation of work provided and <br /> installed by Owner. Unless otherwise expressly authorized in writing by the Owner's Representative,the <br /> Contractor must integrate the schedules with the Schedule of Values and unit price items so that each <br /> construction activity is represented by a dollar value. <br /> Float in a Progress Schedule belongs to the Owner. <br /> Subcontractors shall review all schedules prior to submission to the Owner and Owner's Representative. <br /> At the Owner's option and sole discretion, Owner may require Contractor to obtain written acceptance of <br /> each schedule by Subcontractors as practical and feasible, as the schedule relates to Subcontractors' work. <br /> Contractor shall not schedule any activity with an unrealistic,unduly long,or unduly short duration. <br /> Contractor shall use its best efforts in good faith to set reasonable durations for all activities. Contractor <br /> General Conditions—007200-16 <br /> I <br />