Laserfiche WebLink
I <br /> Revised 2021-01-19— <br /> Addendum No. 1 <br /> shall not attempt to"grab the Float"or make any effort to use any Float in the Progress Schedule for the <br /> benefit of the Contractor. <br /> Contractor shall submit with each Application for Payment or progress pay estimate an updated Progress <br /> Schedule,but no less often than monthly. If requested by the Owner's Representative or the Owner, <br /> Contractor shall prepare and submit updated Progress Schedules from time to time,which may be more <br /> frequent than monthly. <br /> The Contractor hereby expressly agrees and acknowledges that any failure by Contractor to provide <br /> accurate,complete,current and updated schedules with each and every progress pay estimate or <br /> Application for Payment constitutes a waiver of any and all claims or requests for adjustment of Contract <br /> Sum or Time that arise out of,result from, or are caused by,any Delay on the Project or scheduling of the <br /> ' Work. Timely submission of monthly updated schedules is a condition precedent to any later or <br /> subsequent Contract Claim or request for an adjustment of either Contract Sum or Time related to or <br /> arising out of time,an alleged Delay, or the schedule or sequence of Work. Similarly,the parties agree <br /> the Owner may withhold progress pay estimates if updated schedules are not timely submitted. These <br /> remedies are cumulative and not exclusive of any other remedy. The Owner's use of one or more of these <br /> remedies does not constitute an election or prevent the Owner from pursuing other remedies for this or <br /> other defaults. <br /> ' The Owner's Representative's review of any schedule shall not transfer any of the Contractor's <br /> responsibilities to the Owner. The Contractor alone shall remain responsible for adjusting forces, <br /> ' equipment,and work schedules to ensure completion of the Work within the Contract Time. Review by <br /> the Owner or Owner's Representative shall not constitute approval or acceptance of the Contractor's <br /> construction means,methods, sequencing,logic, order,precedence and succession of activities or <br /> Contractor's ability to complete the Work in a timely manner. Any mistakes or errors in any schedule, <br /> including,but not limited to, mistakes or errors of logic,order,precedence,and duration,are and remain <br /> the Contractor's. The Owner or Owner's Representative may comment upon the schedule. <br /> 5.2.2.2 Extensions of Contract Time <br /> Any requests for extensions in Contract Time,whether resulting from Extra Work directed by the Owner <br /> or not, shall be accompanied by an analysis of schedules using the critical path method. This analysis <br /> shall include an updated schedule, an as-planned schedule, an as-built schedule,a but-for schedule,and <br /> narrative explaining the alleged causes, schedule impacts and all costs related to or arising out of the <br /> proposed extension. Any requests for extensions of Contract Time by the Contractor shall be submitted in <br /> accordance with these General Conditions. Extensions of Contract Time will be granted only as provided <br /> in the General Conditions and to the extent that affected critical activities exceed the Total Float time <br /> along the affected paths of the reviewed Preliminary Schedule at the time the change was authorized in <br /> writing by the Owner. Contractor has the burden of clearly and convincingly demonstrating entitlement <br /> to any adjustment of Contract Time. <br /> If the Owner is solely responsible for any Delay to Substantial Completion,Physical Completion, <br /> Completion Date, or Final Acceptance,the Contractor shall only be entitled to compensation or other <br /> 1 damages as described in 12.4 REMEDIES,provided that Contractor timely gave Notice pursuant to 10. <br /> NOTICE TO OWNER,timely submitted a Contract Claim pursuant to 12. CONTRACT CLAIMS and <br /> fulfilled the requirements of 5.2.2.Construction Schedule. <br /> 1 5.2.3. Construction Progress <br /> The Contractor shall furnish all labor,materials,facilities and Equipment necessary to insure the <br /> prosecution and completion of the Project within the interim milestones, Substantial Completion,Physical <br /> ' Completion and Completion Dates of the Contract. If Work falls seven(7) days or more behind the <br /> reviewed Preliminary Schedule,the Contractor agrees that, at its sole cost and expense, it will take all <br /> actions necessary to return the Project to the accepted schedule. These actions may include the following: <br /> 1. Increase labor in quantities and crafts. <br /> General Conditions—007200-17 <br /> I <br />