CITY OF EVERETT SPECIAL PROVISIONS <br /> Contractor shall submit an updated progress schedule for review by the City and City's <br /> Representative, at the weekly construction meeting or as otherwise as requested by City's <br /> Representative or City. Any deviation from the Baseline Schedule shall be explained by the <br /> Contractor, including the cause and effect of the deviation. Contractor shall state in writing <br /> the corrective measures it will take to bring the progress of the Work back in line with the <br /> Baseline Schedule. <br /> Once an actual start or completion date is stated in a submitted progress schedule, <br /> Contractor shall not change schedule without prior written agreement of the City and City's <br /> Representative. <br /> With each submitted updated progress schedule, Contractor shall provide a written narrative <br /> report that identifies anticipated or actual deviations from the Baseline Schedule, causes of <br /> the deviations, and the impact of the deviations on the schedule and describes the corrective <br /> action taken or proposed, and its effect. <br /> 1-08.3(3) Schedule Updates <br /> Delete 1-08.3(3) and substitute the following: <br /> 1-08.3(3) Schedule Format and Content <br /> (******) <br /> 1-08.3(3)A Schedule Format <br /> All schedules shall be in the following form: <br /> 1. Network analysis system using the current version of Microsoft Project software <br /> and the critical path method, as outlined in The Associated General Contractors of <br /> America (AGC) publication "The Use of CPM in Construction -A Manual for <br /> General Contractors." <br /> 2. Sequence of Listings: The chronological order of the start of each activity of Work. <br /> Listings on Progress Schedule and Schedule of Values shall be the same. <br /> 3. Scale and Spacing: To provide space for notations and revisions. <br /> 4. Each schedule and update shall be provided in three (3) paper copies and one <br /> electronic copy in current Microsoft Project format. Paper copies shall be on a <br /> single sheet of paper and of sufficient size to allow legibility of schedule. Pieces of <br /> the schedule on separate sheets of paper that must be taped together to form <br /> schedule are not permitted. Electronic copies shall be submitted on either <br /> separate CD-ROMs or as email attachment to City's Representative. <br /> 5. Updated Progress Schedules shall indicate progress of the Work to the date of <br /> submission by drawing a vertical line down the schedule to represent Work <br /> completed to date. <br /> 1-08.3(3)B Schedule Contents <br /> All Progress Schedules shall: <br /> 1. Include essential sub-schedules of related activities. <br /> 2. Allow for timely incorporation of any other's work under separate contract with <br /> City. <br /> 3. Allow for timely incorporation of work provided and installed by City. <br /> 4. Include submittals to agencies required for performance of Work with sufficient, <br /> adequate and reasonable time for review, comment and return submittals. <br /> 5. Allow for appropriate durations to complete activities that may be affected by <br /> weather during the time of year the activities are performed. <br /> SEI to SRI Intertie,SRO8 Rehab Division 1 —GENERAL REQUIREMENTS WO No.—UP3714 <br /> SP-92 <br /> I <br />