Laserfiche WebLink
CITY OF EVERETT SPECIAL PROVISIONS <br /> If the Engineer determines that the Contractor failed to pursue the Work diligently before the <br /> suspension, or failed to comply with the Contract or orders, then the Contractor shall maintain the <br /> temporary roadway, sidewalk, and path in use during suspension. In this case, the Contractor <br /> shall bear the maintenance costs. If the Contractor fails to maintain the temporary roadway, <br /> sidewalk, and path the City will do the Work and deduct all resulting costs from payments due to <br /> the Contractor. <br /> If the Engineer determines that the Contractor has pursued the Work diligently before the <br /> suspension, then the City will maintain the temporary roadway, sidewalk, and path (and bear its <br /> cost). This City-provided maintenance work will include only routine maintenance of: <br /> 1. The Traveled Way,Auxiliary Lanes, Shoulders, detour surface, sidewalks, and paths, <br /> 2. Roadway drainage along and under the traveled Roadway, sidewalk, path or detour, <br /> and <br /> 3. All barricades, signs, and lights needed for directing traffic through the temporary <br /> Roadway, sidewalk, path or detour in the construction area. <br /> The Contractor shall protect and maintain all other Work in areas not used by traffic. All costs <br /> associated with protecting and maintaining such Work shall be the responsibility of the Contractor <br /> except those costs associated with implementing the TESC Plan according to Section 8-01. <br /> After suspension during which the City has done the routine maintenance, the Contractor shall <br /> accept the traveled Roadway,sidewalk, path or detour as is when Work resumes. The Contractor <br /> shall make no claim against the City for the condition of the Roadway or detour. <br /> After any suspension, the Contractor shall resume all responsibilities the Contract assigns for the <br /> Work. <br /> 1-08.8 Extensions of Time <br /> Delete the first and second sentences in the second paragraph of 1-08.8. ' <br /> Supplement 1-08.8 by adding the following: <br /> Any requests for extensions in Contract Time, whether resulting from Extra Work directed by the <br /> City or not, shall be accompanied by an analysis of schedules using the critical path method.This <br /> analysis shall include an updated schedule, an as-planned schedule, an as-built schedule, a but- <br /> for schedule, and narrative explaining the alleged causes, schedule impacts and all costs related <br /> to or arising out of the proposed extension. Any requests for extensions of Contract Time by the <br /> Contractor shall be submitted in accordance with these Contract Documents. Extensions of <br /> Contract Time will be granted only as provided in the Contract Documents and to the extent that <br /> affected critical activities exceed the Total Float time along the affected paths of the reviewed <br /> Preliminary Schedule at the time the change was authorized in writing by the City. Contractor <br /> has the burden of clearly and convincingly demonstrating entitlement to any adjustment of <br /> Contract Time. <br /> If the City is solely responsible for any Delay to Substantial Completion, Physical Completion, <br /> Completion Date, or Final Acceptance, the Contractor shall only be entitled to compensation or <br /> other damages as described in 1-09.11A REMEDIES, provided that Contractor timely gave Notice <br /> pursuant to 1-04.5 NOTICE BY CONTRACTOR, timely submitted a Contract Claim pursuant to <br /> 1-09.11(2) CONTRACT CLAIMS and fulfilled the requirements of 1-08.3 PROGRESS <br /> SCHEDULE. <br /> 1-08.9 Liquidated Damages , <br /> Revise the fourth paragraph of 1-08.9 to read as follows: <br /> When the Contract Work has progressed to Substantial Completion as defined in the Contract, <br /> the Engineer may determine that the work is Substantially Complete. The Engineer will notify the <br /> Contractor in writing of the Substantial Completion Date. For overruns in Contract time occurring <br /> after the date so established, the formula for liquidated damages shown above will not apply. For <br /> SEI to SRI Intertie,SR08 Rehab Division 1 -GENERAL REQUIREMENTS WO No.-UP3714 <br /> SP-98 <br /> I <br />