I <br /> I CITY OF EVERETT SPECIAL PROVISIONS <br /> In such event, the City will review the City's Representative's certification that the Work is <br /> substantially complete. If the City concurs, the City will notify the Contractor in writing that the <br /> I Work is accepted as substantially complete. Except for any portion(s) of Work specified for early <br /> completion or required by the City for early possession, Substantial Completion will not occur for <br /> Work until the entire Project is ready for possession and use. The acceptance Notice will include <br /> I a Punch List of incomplete Work items and corrective Works, set the date for their completion <br /> and repair, describes the division of responsibility between the City and Contractor, and describe <br /> other terms of acceptance. The Contractor will acknowledge receipt of the acceptance Notice in <br /> I writing, indicating acceptance of all of its terms and provisions. <br /> Subsequent to the Substantial Completion date, the City may exclude the Contractor from the <br /> Work during such periods when construction activities might interfere with the intended operation <br /> of the Project. The City, however, shall allow the Contractor reasonable access for completion or <br /> I <br /> correction of incomplete Punch List items. <br /> 1-08.5(3) Acceptance of Work <br /> (******) <br /> IUpon completion of the Project, including, but not limited to, record drawings, as-builts, required <br /> reports and operations and maintenance manuals, the Contractor shall so notify the City's <br /> Representative in writing. Upon receipt of the notification, the City's Representative will promptly, <br /> I <br /> by personal inspection, determine the actual status of the Work in accordance with the terms of <br /> the Contract. If the City's Representative finds materials, Equipment, or workmanship that do not <br /> meet the terms of the Contract, it will prepare a Punch List of such items and submit it to the <br /> I Contractor. Following completion of the corrective work by the Contractor, the City's <br /> Representative will notify the City that the Work has been completed in accordance with the <br /> Contract. The City shall make the final determination of acceptability and completion. For <br /> portions of the Project not previously accepted as substantially complete, the conditions of <br /> Iguarantee shall commence on the date that the City determines the Project is complete. <br /> 1-08.6 Suspension of Work <br /> I Supplement 1-08.6 by adding the following: <br /> 1-08.6(1) Suspension Procedures <br /> (******) <br /> I The City may, at its convenience and at any time and without cause, suspend all or any part of <br /> the Work by notice in writing to the Contractor. The Contractor shall resume the Work within five <br /> (5) calendar days after receiving written notice from the City to do so. The Contractor will be <br /> I allowed an increase in the Contract Sum or an extension of Contract Time, or both, directly <br /> attributable to any suspension in accordance with the Change Order procedures in these Special <br /> Provisions; provided, (1)the Contractor shall not be entitled to any increase to the extent caused <br /> by the Contractor and (2) Contract Sum increases and Contract Time extensions for suspension <br /> I <br /> caused by Third Parties or Force Majeure Events are limited as set forth in 1-09.11A(3)D THIRD <br /> PARTY CAUSED DELAYS AND FORCE MAJEURE. <br /> 1-08.7 Maintenance During Suspension <br /> IDelete all of 1-08.7 and substitute the following: <br /> Before and during any suspension (as described in Section 1-08.6) the Contractor shall protect <br /> the Work from damage or deterioration. Suspension shall not relieve the Contractor from anything <br /> lthe Contract requires unless this Section states otherwise. <br /> At no expense to the City, the Contractor shall provide through the construction area a safe, <br /> smooth, and unobstructed roadway, sidewalk, and path for public use during suspension, as <br /> I required in 1-07.23 PUBLIC CONVENIENCE AND SAFETY. This may require a temporary road <br /> or detour. <br /> I SEI to SRI Intertie,SRO8 Rehab Division 1 —GENERAL REQUIREMENTS WO No.—UP3714 <br /> SP—97 <br /> I <br />