I <br /> CITY OF EVERETT SPECIAL PROVISIONS <br /> 4. The Contractor believes, or with the reasonable exercise of ordinary care should <br /> believe, it is entitled to an adjustment of Contract Sum or Time, even if the total or <br /> ' exact amount or impact cannot yet be determined; <br /> 5. The Contractor believes it is required or directed to perform work that is outside the <br /> scope of the Contract Documents; or <br /> ' 6. An event occurs, or fails to occur, that the Contractor believes, or should reasonably <br /> foresee, may result in a Contract Claim; or <br /> 7. The actual quantities of Unit Price Work vary sufficiently from the original estimate that <br /> Contractor may be entitled to an equitable adjustment of Contract Sum as provided in <br /> 1-04.6 VARIATION IN INCREASED OR DECREASED QUANTIES; <br /> The Contractor shall immediately give Notice to the City or City's Representative as provided in <br /> ' this section and elsewhere in the Contract Documents and Specifications. <br /> Timely and adequate Notice is a condition precedent to a Contract Claim. <br /> Requests for extensions of Contract Time shall be made and evaluated in accordance with 1- <br /> 08.3 PROGRESS SCHEDULE and 1-08.8 EXTENSIONS OF TIME. <br /> Irrespective of any request for additional compensation or Contract Time or a Contract Claim that <br /> Work is extra and not part of the original scope of Work, the Contractor shall proceed <br /> expeditiously and promptly with the Work as the City orders. <br /> If the Contractor fails to follow the procedures of this Contract, including failing to give Notice, the <br /> Contractor completely waives any Contract Claims. In its sole discretion, the City may waive <br /> ' strict compliance with procedures, but any such waiver of one or more items or elements does <br /> not waive the necessity for Contractor's strict compliance with any other item or element, nor shall <br /> such waiver be admissible in any legal proceeding for any reason. <br /> ' 1-04.5(2) Form of Notice <br /> The Notice shall be in writing and include the following minimum information: <br /> 1. A complete and accurate description of the event(s) giving rise to the Notice, including <br /> dates, times, and locations; <br /> 2. A preliminary list of persons involved in such event; <br /> 3. A statement whether the Contractor believes the event may result in a Contract Claim <br /> ' for additional Contract Time or adjustment of the Contract Sum; <br /> 4. A date by which Contractor shall begin providing Supplemental Information as <br /> provided in this section. <br /> 1-04.5(3) Supplemental Information <br /> Contractor shall supplement the written Notice as soon as possible with a written statement <br /> providing the following: <br /> 1. The date of the event, incident, direction, instruction, interpretation or determination; <br /> 2. The nature and circumstances giving rise to the Notice; <br /> 3. The contract provisions relating to the event, incident, direction, instruction, <br /> ' interpretation or determination; <br /> 4. The estimated dollar cost, if any, of the Extra Work, Delay, change or disruption and <br /> detailing how the dollar amount estimate was determined; and <br /> ' 5. An analysis of the progress schedule showing the impact to the schedule resulting <br /> from the change or disruption, if the Contractor is asserting a schedule change or <br /> disruption; <br /> Throughout any work related to a Notice, the Contractor shall keep complete and accurate <br /> records of costs, expenses, and time incurred for which Contractor will or may seek an <br /> ' SEI to SRI Intertie,SR08 Rehab Division 1 —GENERAL REQUIREMENTS WO No.—UP3714 <br /> SP-55 <br /> f <br />