the Owner will review the Owner's Representative's certification that the Work is <br /> substantially complete. If the Owner concurs, the Owner will notify the Contractor in <br /> writing that the Work is accepted as substantially complete. Except for any portion(s) of <br /> Work specified for early completion or required by the Owner for early possession, <br /> Substantial Completion will not occur for any Work until the entire Project is ready for <br /> possession and use. The acceptance notice will include a Punch List of incomplete Work <br /> items and corrective Work, set the date for their completion and repair, describe the <br /> division of responsibility between the Owner and Contractor, and describe any other terms <br /> of acceptance. The Contractor will acknowledge receipt of the acceptance notice in <br /> writing, indicating acceptance of all of its terms and provisions. <br /> C. Subsequent to the Substantial Completion date, the Owner may exclude the Contractor <br /> from the Work during such periods when construction activities might interfere with the <br /> intended operation of the Project. The Owner, however, shall allow the Contractor <br /> reasonable access for completion or correction of incomplete Punch List items. <br /> 5.8 Acceptance of Work <br /> A. Upon completion of the Project, including, but not limited to, record drawings, as-builts, <br /> required reports and operations and maintenance manuals, the Contractor shall so notify <br /> the Owner's Representative in writing. Upon receipt of the notification, the Owner's <br /> Representative will promptly, by personal inspection, determine the actual status of the <br /> Work in accordance with the terms of the Contract. If the Owner's Representative finds <br /> materials, Equipment, or workmanship that do not meet the terms of the Contract, he or <br /> she will prepare a Punch List of such items and submit it to the Contractor. Following <br /> completion of the corrective Work by the Contractor, the Owner's Representative will <br /> notify the Owner that the Work has been completed in accordance with the Contract. The <br /> Owner shall make the final determination of acceptability and completion. For portions of <br /> the Project not previously accepted as substantially complete, the conditions of guarantee <br /> shall commence on the date that the Owner determines the Project is complete. <br /> ARTICLE 6 CHANGES <br /> 6.1 Owner's Right to Direct Changes to the Work <br /> A. The Owner reserves the right to change the Work at any time. Such changes shall not <br /> invalidate the Contract nor release the surety, and the Contractor agrees to perform the <br /> Work as changed. Among others, these changes and alterations may include: <br /> 1. Deleting or omit any part of the Work, Equipment or material to be provided under <br /> this Contract, <br /> 2. Increasing or decreasing quantities, <br /> 3. Altering Specifications, designs, or both, <br /> 4. Altering the way the Work is to be done, <br /> 5. Adding new Work or Extra Work, <br /> Replacement of Reservoir 2 General Conditions <br /> WO# UP3658 00 72 13 - 33 <br />