Laserfiche WebLink
1) Extensions of Contract Time caused by Extra Work shall be determined as <br /> provided in 5.2.C. Extensions of Contract Time. <br /> C. Delays <br /> 1. Owner Caused Delay Unrelated to Extra Work <br /> a. Adjustment of Contract Sum <br /> 1) If the Contractor is entitled to an adjustment of Contract Sum because of a <br /> Delay solely caused by the Owner that does not relate to Extra Work, <br /> Contractor shall only be compensated for the items below, less all funds <br /> paid pursuant to any change in the Contract Sum that contributed to the <br /> Delay: <br /> a) Documented, incurred cost of nonproductive field supervision or labor <br /> extended because of the Delay; <br /> b) Documented, incurred cost of home office supervision to attend <br /> jobsite meetings; <br /> c) Documented, incurred cost of temporary facilities or equipment rental <br /> extended because of the Delay; <br /> d) Documented, incurred cost of insurance extended because of the <br /> Delay; <br /> e) General and administrative Overhead in an amount to be agreed upon, <br /> but not to exceed three percent (3%) of original Contract Sum divided <br /> by the Contract Time for each day of the Delay. <br /> 2) Owner shall not owe Contractor compensation for extended Overhead or <br /> other delay costs where Contractor contributed to or is concurrently <br /> responsible for the Delay. <br /> b. Adjustment of Contract Time <br /> 1) If the Contractor is entitled to an adjustment of Contract Time because of a <br /> Delay solely caused by the Owner that does not relate to Extra Work, <br /> Contractor shall be entitled to an adjustment of Contract Time to the extent <br /> the Delay increases the duration of the Project, as measured by the critical <br /> path and as demonstrated pursuant to the requirements of 5.2.C. <br /> Extensions of Contract Time. <br /> 2. Contractor Caused Delay <br /> a. If the Contractor is solely responsible for any Delay to any interim milestone, <br /> Substantial Completion, Physical Completion or the Completion Date, the Owner <br /> shall be entitled to liquidated or other damages as provided elsewhere in the <br /> Contract Documents. <br /> b. The Contractor accepts the risk of any Delays caused by strikes, work slowdowns, <br /> job actions and labor unrest of any kind. <br /> c. Contractor shall not be entitled to any increase in Contract Sum or Contract Time <br /> due to a Delay it caused. <br /> 3. Delays Concurrently Caused by Contractor and Owner <br /> a. If the Owner and the Contractor cause a Delay concurrently, neither the Owner <br /> nor the Contractor shall be liable to the other except as provided herein. <br /> Replacement of Reservoir 2 General Conditions <br /> WO# UP3658 00 72 13 - 66 <br />