My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
Thomco Construction Inc. 6/14/2021
>
Contracts
>
Capital Contract
>
Thomco Construction Inc. 6/14/2021
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
6/23/2022 10:53:29 AM
Creation date
6/18/2021 10:03:52 AM
Metadata
Fields
Template:
Contracts
Contractor's Name
Thomco Construction Inc.
Approval Date
6/14/2021
Council Approval Date
5/19/2021
Department
Public Works
Department Project Manager
Amie Roshak
Subject / Project Title
Water Main Replacement V
Public Works WO Number
UP3730
Tracking Number
0002953
Total Compensation
$1,924,004.26
Contract Type
Capital Contract
Retention Period
10 Years Then Transfer to State Archivist
Document Relationships
Thomco Construction Inc. 6/22/2022 Change Order 1
(Contract)
Path:
\Documents\City Clerk\Contracts\Capital Contract
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
492
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
CITY OF EVERETT SPECIAL PROVISIONS <br /> 1-09.11A(3) Delays <br /> 1-09.11A(3)A City Caused Delay Unrelated to Extra Work <br /> 1-09.11A(3)A1 Adjustment of Contract Sum <br /> If the Contractor is entitled to an adjustment of Contract Sum because of a <br /> Delay solely caused by the City that does not relate to Extra Work, Contractor <br /> shall only be compensated for the items below, less all funds paid pursuant to <br /> any change in the Contract Sum that contributed to the Delay: <br /> 1. Documented, incurred cost of nonproductive field supervision or <br /> labor extended because of the delay; <br /> 2. Documented, incurred cost of home office supervision to attend <br /> jobsite meetings; <br /> 3. Documented, incurred cost of temporary facilities or equipment <br /> rental extended because of the Delay; <br /> 4. Documented, incurred cost of insurance extended because of the <br /> Delay; <br /> 5. General and administrative overhead in an amount to be agreed <br /> upon, but not to exceed three percent of original Contract Sum <br /> divided by the Contract Time for each day of the Delay. <br /> City shall not owe Contractor compensation for Extended Overhead or other <br /> >� delay costs to the extent Contractor or anyone other than the City contributed <br /> to or is concurrently responsible for the Delay. <br /> 1-09.11A(3)A2 Adjustment of Contract Time <br /> If the Contractor is entitled to an adjustment of Contract Time because of a <br /> Delay solely caused by the City that does not relate to Extra Work, Contractor <br /> shall be entitled to an adjustment of Contract Time to the extent the Delay <br /> increases the duration of the Project, as measured by the critical path and as <br /> demonstrated pursuant to the requirements of 1-08.8 EXTENSIONS OF TIME. <br /> 1-09.11A(3)B Contractor Caused Delay <br /> If the Contractor is solely responsible for any Delay to any interim milestone, <br /> Substantial Completion, Physical Completion, or the Completion Date, the City shall <br /> be entitled to liquidated or other damages as provided elsewhere in the Contract <br /> 1 Documents. The Contractor accepts the risk of any Delays caused by strikes, work <br /> slowdowns,job actions and labor unrest of any kind. Contractor shall not be entitled <br /> to any increase in Contract Sum or Contract Time due to a Delay it caused. <br /> 1-09.11A(3)C Delays Concurrently Caused by Contractor and Owner <br /> If the City and the Contractor cause a Delay concurrently, neither the City nor the <br /> Contractor shall be liable to the other except as provided herein. <br /> 1-09.11A(3)C1 Adjustment of Contract Sum <br /> The Contractor shall not be entitled to any adjustment in Contract Sum for <br /> Delays concurrently caused by the City and the Contractor. <br /> 1-09.11A(3)C2 Adjustment of Contract Time <br /> The Contractor shall be entitled to an extension of Contract Time for the City <br /> caused portion of any Delay concurrently caused by the City and Contractor to <br /> the extent the City caused the Delay to extend longer than if the Contractor had <br /> solely caused the Delay. <br /> Water Main Replacement"V" Division 1 -GENERAL REQUIREMENTS April,2021 <br /> WO No-UP3730 SP-119 <br /> I <br />
The URL can be used to link to this page
Your browser does not support the video tag.