I <br /> CITY OF EVERETT SPECIAL PROVISIONS <br /> 1-09.11A(3)D Third Party Caused Delays and Force Majeure <br /> For the purposes of this section 1-09.11A(3)D, a "Force Majeure Event" is I <br /> defined as earthquake, flood, pandemic (and governmental laws, regulations, <br /> requirements, and orders resulting therefrom), natural disasters, acts of war <br /> or acts of terrorism. Pandemic in the preceding sentence includes without <br /> limitation the COVID-19/ novel coronavirus (SARS-CoV-2) pandemic, which <br /> is the subject of the Governor's proclamation dated February 29, 2020, and <br /> subsequent proclamations. <br /> For the purposes of this section 1-09.11A(3)D, a "Third Party" is defined as a <br /> third party for whom neither the Contractor nor the City is responsible. <br /> 1-09.11A(3)D1 Adjustment of Contract Sum <br /> The City and the Contractor shall not be responsible to compensate each <br /> other financially for any Delay to the extent caused by a Third Party or a <br /> Force Majeure Event. A Delay caused by a utility's failure to provide <br /> service or relocate its lines (despite a timely request for such service or <br /> relocation) is an example of this kind of Delay for which neither the <br /> Contractor nor the City is financially responsible to the other. Mislocated <br /> utility lines or utility lines not located are another example of a Delay for <br /> which neither the Contractor nor the City is responsible to the other. <br /> However, the Contractor's failure to request a utility locate or relocation in <br /> a timely way is not, and any resulting Delay would be the responsibility of <br /> the Contractor. Because the Contractor is responsible for ordering <br /> materials and Equipment, Contractor shall not be entitled to an <br /> adjustment of Contract Time or Contract Sum due to Delays caused by <br /> the lack of materials or Equipment. A strike,job action, slowdown, work <br /> to rule, or other job action or labor dispute or problem is not a Delay <br /> caused by a Third Party. <br /> 1-09.11A(3)D1 Adjustment of Contract Time <br /> The Contractor shall be entitled to an extension of Contract Time for <br /> Delays to the extent caused by a Third Party or a Force Majeure Event. <br /> Extension of Contract Time shall be determined pursuant to 1-08.8 <br /> EXTENSIONS OF TIME. <br /> 1-09.11A(4) Extended or Unabsorbed Overhead I <br /> 1-09.11A(4)A General <br /> To present a request for additional compensation for Extended or Unabsorbed <br /> Overhead, the Contractor has the burden of keeping and maintaining accurate <br /> documentation to support any such claim. If the Contractor fails to provide or keep <br /> inadequate financial data for an accurate and fair Eichleay calculation, Contractor <br /> waives and releases any claim for Unabsorbed or Extended Overhead. In <br /> presenting any claim under this section of the Contract, the Contractor agrees to <br /> provide to the City any and all financial data needed by the City, or its <br /> representative, to review, substantiate and evaluate any claim for Extended or <br /> Unabsorbed Home Office Overhead, or both. Failure to provide the requested <br /> information shall constitute waiver by the Contractor. <br /> If Contractor is entitled to an adjustment of Contract Sum for Unabsorbed or <br /> Extended Overhead, it shall be calculated as provided in these Special Provisions. <br /> Water Main Replacement"V" Division 1 —GENERAL REQUIREMENTS April,2021 <br /> WO No—UP3730 SP—120 <br /> 1 <br />