CITY OF EVERETT SPECIAL PROVISIONS <br /> types and amounts of Contractor Overhead Costs on no greater <br /> than a monthly basis for the actual Project duration. <br /> 1-09.11 A(4)A1 c Overabsorbed Overhead <br /> To demonstrate that Contractor did not incur Overabsorbed Overhead in <br /> the period following the Delay, in accordance with item 5 of 1- <br /> 09.11A(4)A1. of these Special Provisions, the Contractor shall: <br /> 1. Affirmatively represent and warrant that completion of the <br /> delayed Work prevented the performance of other Work; <br /> 2. Identify the critical resource unavailable for other Work due to <br /> completion of the delayed Contract; and <br /> 3. Showing that unavailability of this critical resource precluded the <br /> performance of other Work. <br /> 1-09.11 A(5) Inefficiencies <br /> 1-09.11A(5)A Adjustment of Contract Sum <br /> To the extent Contractor is entitled to an increase in Contract Sum because of <br /> inefficiencies or impaired productivity, then compensation due shall be <br /> calculated as provided in 1-09.4 EQUITABLE ADJUSTMENT. <br /> 1-09.11A(5)B Adjustment of Contract Time <br /> To the extent Contractor is entitled to an extension of Contract Time because <br /> of inefficiencies or impaired productivity,then the extension shall be determined <br /> as provided in 1-08.8 EXTENSIONS OF TIME. <br /> Delete all of 1-09.12 and substitute the following: <br /> 1-09.12 Audits <br /> (******) <br /> 1-09.12(1) General <br /> The Contractor's records relating to this Project, including, but not limited to, wage, I <br /> payroll, and cost records, shall be open to inspection or audit by representatives of the <br /> City during the Project and for a period of not less than six years after the date of Final <br /> Acceptance of the Contract. The Contractor shall retain these records for that period. <br /> The Contractor shall also guarantee that Project records of Subcontractors, suppliers, <br /> and lower tier subcontractors, including, but not limited to, the wage, payroll, and cost <br /> records, shall be retained and open to similar inspection or audit for the same period of <br /> time. The audit may be performed by employees or representatives of the City or by an <br /> auditor chosen by the City. The Contractor, Subcontractors, or lower tier subcontractors <br /> shall provide adequate facilities, reasonably acceptable to auditor, for the audit during <br /> normal business hours. The Contractor, Subcontractors, or lower tier subcontractors <br /> shall make a good faith effort to cooperate with the auditors. If an audit is to be <br /> commenced more than 60 calendar days after the Final Acceptance date of the Contract, <br /> the Contractor will be given 20 calendar days' notice of the time when the audit is to <br /> begin. If any litigation, claim, or audit arising out of, in connection with, or related to this <br /> Contract is initiated, the Project records shall be retained until the later of(a) completion <br /> of litigation, claim, or audit or(b) six years after the date of Final Acceptance. <br /> 1-09.12(2) Claims <br /> All Contract Claims filed against the City shall be subject to audit at any time following <br /> the filing of the Contract Claim. Failure of the Contractor, Subcontractors, or lower tier <br /> subcontractors to maintain and retain sufficient records to allow the auditors to verify all <br /> or a portion of the Contract Claim or to permit the auditor access to the books and <br /> Water Main Replacement"V" Division 1 —GENERAL REQUIREMENTS April,2021 <br /> WO No—UP3730 SP—122 <br />