Exhibit A—Description of Changed Work <br /> On April 22nd, 2021, the City terminated the Contract for convenience. This resulted in <br /> deletion of remaining work, which had value of $251 ,041 .98. Therefore, $251 ,041 .98 is <br /> subtracted from the Contract Sum. The parties agree that the Contractor had costs <br /> related to the termination for convenience in the amount of $14,368.97. Therefore, <br /> $14,368.97 is added to the Contract Sum. Accordingly, this change order subtracts a <br /> total of $236,673.01 from the Contract Sum, not including Washington State Sales tax. <br />