NKC Everett <br />Everett, Washington Drainage Memorandum <br />Element 3: Control Flow Rates <br />As noted above, site demolition and improvements associated with this project will be limited, <br />with less than 2,000 SF of land disturbed by the project. Existing vegetation is well established <br />in the vicinity of the proposed site improvements and will be protected wherever possible to <br />control the rates of runoff leaving the site. Flow rates are not anticipated to be significantly <br />affected by the proposed construction activities. <br />Element 4: Install Sediment Controls <br />As described in previous sections, the majority of the property will remain paved or covered in <br />well -established vegetation throughout construction, greatly reducing the risk sediment -laden <br />runoff leaving the site and entering the storm system. <br />As a precaution, the inlets and catch basins in the vicinity of the project will be protected from <br />sediment using storm drain inlet protection per City of Everett Standard Plan 210. If necessary, <br />the contractor will implement additional City of Everett Standard sediment control BMPs as <br />necessary to prevent sediment from leaving the site, see Element 7 below for more information. <br />Element 5: Stabilize Soils <br />The proposed project involves only minor grading activities that will not result in soils being <br />exposed for,extended periods of time. As described in previous sections, existing pavement and <br />vegetation will be maintained to the maximum extent feasible, keeping soils covered and <br />minimizing the risk of erosion. <br />Element 6: Protect Slopes <br />Based on the scope of the proposed site work, significant slopes are not anticipated as a part of <br />this project, Element 6 is not applicable. <br />Element 7: Protect Drain Inlets <br />Storm drain catch basins and inlets will be protected per City of Everett Standard Plan 210. If <br />necessary, additional inlet protection will be implemented through the use of the following <br />BMPs: <br />• City of Everett Standard Plan 212: Inlet Fabric Fence Filter <br />• City of Everett Standard Plan 214: Temporary Silt Fence <br />Element 8: Stabilize Channels and Outlets <br />The existing site drains via sheet flow over paved surfaced to catch basins, which collect runoff <br />before it is conveyed off -site. Channels and outlets will not be affected by the project; Therefore <br />Element 8 is not applicable. <br />Element 9: Control Pollutants <br />The project is not anticipated to be a source of pollutants; Therefore Element 9 is not applicable. <br />KPFF Consulting Engineers December 11, 2019 <br />Page 2 of 4 <br />