• 0 <br />Mr. Mark Thunberg <br />Snohomish County Property Management <br />Plan Check Number: B1802-011, First Review (Structural) <br />June 18, 2018 <br />c. Elevation 15/S-321 references Detail 17/S-321, which is not provided. <br />d. Detail 18/S-321 shows a WT connected to the existing beam, with the WT-flange <br />overlapping the existing beam bottom flange. The calculations show the WT-web <br />connected to the flange. <br />e. Detail 16/S-321 shows a WT connected to the existing beam. The orientation should be <br />verified. <br />f. Calculations for the connection in Details 8/S-321 and 13/S-321 should be submitted. <br />g. The design requires multiple braces to be supported by existing beams. Calculations for <br />beams supporting brace loads should be submitted for review. <br />h. The penthouse design considers only seismic loading. Wind loading should be evaluated, <br />especially in the transverse direction. <br />37. The support framing for the cooling tower is shown on Sheet S-206, Partial Plan 14/S-251, and <br />Details 11/S-603 and 16/S-603. Calculations are provided in Section 1.5. See IBC Sections <br />1603.1, 1604.1, and 1604.4. The following comments should be addressed: <br />a. The calculations specify standard P6 for posts. The post size does not appear to be <br />specified in the drawings. <br />b. One W8x24 does not overall a post at the corner of frame per Plan 14/S-251. The plan <br />should be reviewed and revised as needed. <br />c. Calculations should be submitted verifying the capacities of the existing roof beams and <br />columns on Grids D and E supporting the tower. <br />d. The section for the center beam in Plan 14/S-251 is not specified. The beam appears be a <br />composite section per Detail 11/S-603. <br />e. Plan 14/S-251 does not clearly indicate the lateral system in the east -west direction. It <br />appears moment connections at either the top or bottom, or both of the posts is intended <br />per Detail 16/S-603. Calculations substantiating the connections should be submitted for <br />review. <br />f. The calculations assume 50% of the lateral load is tributary to the center beam, and 25% <br />is tributary to the outer beams. The cooling tower appears to be a rigid unit that deflects <br />uniformly across its footprint. The load should be distributed evenly between the frames. <br />g. The calculations appear to specify the outer beams as W8x33. The center beam section is <br />not clear. The drawings specify W8x24 beams, which appear smaller than required by the <br />calculations. Verify the required beam sizes. <br />38. The section of the Structural General Notes titled "Stairs, Elevators and Miscellaneous Metals" <br />on Sheet S-003 states that the design of the connections between the elevator system and the <br />primary structure shall be performed by the elevator manufacturer. The following comments <br />should be addressed: <br />a. The design loads for the elevator system, including impact loading, should be specified in <br />the General Notes. At a minimum, estimated design loads should be specified for the <br />Pa e10of11 <br />CITY OF EVERETT . 3200 Cedar Street • Everett, WA 98201 • (425) 257-8810 • Fax (425) 257-8857 <br />