• <br /> Ms. Finsch <br /> Tiscareno Associates <br /> Plan Check Number: B1801-032, First Review <br /> March 13, 2018 <br /> and details for the backspan connection should be submitted for review. It is <br /> recommended that the stability of the back-span consider Equation 16-10 with a 0.6-factor <br /> on the resisting weight (i.e., floor). See IBC Sections 107.2.1 and 1604.1. <br /> 17. Sheets S209a and S209b show steel HSS columns at Grids S-A/S-7 S-8.3 and S-C/S-7— S-8 <br /> supporting wood-framed construction. Calculations substantiating the design of the columns, <br /> foundations, and connections should be submitted for review. Details for the connections <br /> between the steel and wood framing should be included in the drawings. See IBC Section <br /> 107.2.1 and 1604.1. <br /> 18. Sheet S209a shows floor framing at Grid S-A— S-B/S-7— S-8 that supports a bearing wall and <br /> framing above. The plan also shows a bearing wall below at Grid A-A.7 that appears to bear <br /> on a PSL7 at Level 2 per Sheet S208a. Calculations substantiating the design of the floor <br /> framing should be submitted for review. See IBC Section 1604.1. <br /> 19.The structure includes GL3-1/8 along the corridors. See Sheet S202a for an example. The <br /> beams appear to require hangers similar to the North Building per Section 6/S402. The <br /> structural plans should be reviewed and revised as needed. See IBC Section 107.2.1. <br /> 20. Sheet S208a-SS shows a bearing wall at Grid N.1-1.6/NN.1-A.5 — N.1-B that is continuous to <br /> the roof, and supports substantial areas for Levels 3 and 4 and the Roof. The wall appears to <br /> bear on the Level 2 framing on Sheet S208a. Note that the Level 2 framing provides an <br /> indirect gravity load path through multiple beams. Calculations, including a deflection analysis, <br /> substantiating the design of the framing and connections, including posts and foundations, <br /> should be submitted for review. See IBC Section 1604.1, 1604.3, and 1604.4. <br /> 21.The structure includes prefabricated bolt-on decks on Grids S-A and S.1-3 at Levels 2, 3, and 4. <br /> See Sheet S208b for an example. Section 4/S404 provides a connection for the attachment of <br /> the decks. Calculations substantiating the connection should be submitted for review. See IBC <br /> Section 1604.1. <br /> 22. Section 12/S404 appears to show connections to support a roof structure. The location of this <br /> structure is not clear. The use of this section in the project should be clarified. Documentation <br /> substantiating the design of the roof, including the connections, should be submitted for <br /> review. See IBC Section 1603.1 and 1604.1. <br /> 23. Sheet S210a and S210b show single TJI210 joists at 12-inch spacing west of the shoreline. <br /> The maximum span is 16 feet between Grids S-7 and S-8. Structural calculation page SC132 <br /> requires two joists spanning at 16-inch spacing. Calculations substantiating the joist should be <br /> submitted for review. See IBC Section 1604.2. <br /> 24. Sheet S210a and S210b show PSL5-1/4 and PSL7 along the shoreline. Structural calculation <br /> page SC135 evaluates PSL5-1/4 beams for spans up to 18'-3". The following comments should <br /> be addressed: <br /> a. The typical frame size should be clarified. See IBC Section 1603.1. <br /> b. The spans exceed 18'-3"between S-1 and S-1.6. Calculations substantiating the beam <br /> should be submitted for review. See IBC Section 1604.2. <br /> 5of11 <br /> CITY OF EVERETT • 3200 Cedar Street • Everett, WA 98201 • (425) 257-8810 • Fax(425) 257-8857 <br />