Laserfiche WebLink
City of Everett 00 7200 - 21 <br /> 2022 Biosolids Removal and Disposal UT 3752-30 <br /> 5.4.3. Termination by Contractor after Suspension <br /> ' If the Work has been wholly suspended pursuant to 5.3. Suspension Procedures for more than ninety <br /> (90)days as measured from the date of the notice to suspend,then the Contractor may terminate this <br /> Contract by providing Owner with ten(10)days'Notice that the Contractor shall deem the Contract to be <br /> terminated if the Owner does not provide Contractor with notice to resume Work within those ten(10) <br /> days. Such termination shall be treated as a termination for the Owner's convenience pursuant to 5.4.2. <br /> Termination for Convenience. <br /> 5.4.4. Contractor Obligations upon Termination <br /> On receipt of notice of termination,the Contractor shall immediately discontinue the Work but shall do <br /> such Extra Work as may be ordered by the Owner's Representative or Owner to safeguard the Work then <br /> completed and the materials and Equipment then delivered to the Site of the Work and to leave the Work <br /> in a safe and useful condition. Payment for this Extra Work will be made in accordance with 9.2. <br /> PAYMENT FOR CHANGES. <br /> i5.4.5. Ownership of Materials upon Termination <br /> As of the termination date,whether effected by the Owner or Contractor as provided herein, all the <br /> Contractor's right,title, and interest in and to materials ordered by the Contractor prior to termination, <br /> whether or not they have been delivered to the Site of Work, shall be vested in the Owner, and the <br /> Contractor shall,upon demand of the Owner, execute and deliver to the Owner all requisite bills of sale, <br /> assignments, and other documents of transfer that may be necessary to give effect to the intention of the <br /> itermination procedures set forth above. <br /> 5.4.6. Opportunity to Cure <br /> If the Contractor has not already had an opportunity to cure the default or breach the Owner shall specify <br /> the default or breach and a reasonable period of time to allow the Contractor to cure the default or breach. <br /> The notice of termination will state the time period in which cure is permitted and other conditions as the <br /> Owner, in its sole judgment, shall deem appropriate. If Contractor fails to remedy the breach or default or <br /> any of the terms, covenants, or conditions of this Contract to the Owner's satisfaction within the time <br /> period specified or the Owner shall have the right to terminate the Contract without any further obligation <br /> to the Contractor. Any such termination for default shall not in any way operate to preclude the Owner <br /> from also pursuing all available remedies against Contractor and its sureties for said breach or default. <br /> 5.4.7 Waiver of Remedies for Any Breach <br /> In the event that the Owner elects to waive its remedies for any breach by Contractor or any covenant, <br /> term or condition of this Contract, such waiver by the Owner shall not limit the Owner's remedies for any <br /> succeeding breach of that or of any other term covenant, or condition of this Contract. <br /> 5.5. POSSESSION AND USE OF COMPLETED PORTIONS OF THE WORK <br /> The Owner shall have the right to take possession of and use completed or partially completed portions of <br /> ' the Work even though the time for completing the Work for such portions may not have expired. <br /> Operations and maintenance costs of use of such Work will be borne by the Owner. Such possession and <br /> use shall not be deemed as acceptance of the Work. If such prior possession or use increases the cost of <br /> the Work,the Contractor may be entitled to request extra compensation by giving Notice and following <br /> the procedures of ARTICLE 10. NOTICE TO OWNER and ARTICLE 12. CONTRACT <br /> CLAIMS within five(5) days of each occurrence. The Contractor shall not submit a Contract Claim for <br /> possession by the Owner of portions of the Work specifically required in the Contract Documents to be <br /> placed into use or operation before completion of the entirety of the Work. <br /> 5.6. POSSESSION OF INCOMPLETE PORTIONS OF THE PROJECT <br /> ' Should the Contractor fail to meet any date specified for Substantial Completion of Work or any portion <br /> of work requiring early possession and use by the Owner,the Owner may, after a 10-day notice to the <br /> 00 7200 - 21 GENERAL CONDITIONS <br />