6.3 Withholding of Payments. <br /> 6.3.1 On or before the date established in the Contract, Owner shall pay Design-Builder all <br /> amounts properly due. If Owner determines that Design-Builder is not entitled to all or part of an <br /> Application for Payment as a result of Design-Builder's failure to meet its obligations hereunder, it <br /> will notify Design-Builder in writing at least five(5)days prior to the date payment is due.The notice <br /> shall indicate the specific amounts Owner intends to withhold, the reasons and contractual basis <br /> for the withholding, and the specific measures Design-Builder must take to rectify Owner's <br /> concerns. Design-Builder and Owner will attempt to resolve Owner's concerns prior to the date <br /> payment is due. If the parties cannot resolve such concerns, Design-Builder may pursue its rights <br /> under the Contract Documents, including those under Article 10 hereof. <br /> 6.3.2 Notwithstanding anything to the contrary in the Contract Documents, Owner shall pay <br /> Design-Builder all undisputed amounts in an Application for Payment within the times required by <br /> the Contract. <br /> 6.4 Reserved. <br /> 6.5 Design-Builder's Payment Obligations. <br /> 6.5.1 Design-Builder will pay Design Consultants and Subcontractors, in accordance with its <br /> contractual obligations to such parties, all the amounts Design-Builder has received from Owner <br /> on account of their work. Design-Builder will impose similar requirements on Design Consultants <br /> and Subcontractors to pay those parties with whom they have contracted. Design-Builder will <br /> indemnify and defend Owner against any claims for payment and mechanic's liens as set forth in <br /> Section 7.3 hereof. <br /> 6.6 Substantial Completion. <br /> 6.6.1 Design-Builder shall notify Owner when it believes the Work, or to the extent permitted in <br /> the Contract Documents, a portion of the Work, is Substantially Complete. Within five (5) days of <br /> Owner's receipt of Design-Builder's notice (and all required documents and information), Owner <br /> and Design-Builder will jointly inspect such Work to verify that it is Substantially Complete in <br /> accordance with the requirements of the Contract Documents. If such Work is Substantially <br /> Complete, Owner shall prepare and issue a Certificate of Substantial Completion that will set forth <br /> (i) the date of Substantial Completion of the Work or portion thereof, (ii) the remaining items of <br /> Work that have to be completed before final payment, (iii) provisions (to the extent not already <br /> provided in the Contract Documents) establishing Owner's and Design-Builder's responsibility for <br /> the Project's security, maintenance, utilities and insurance pending final payment, and (iv) an <br /> acknowledgment that warranties commence to run on the date of Substantial Completion, except <br /> as may otherwise be noted in the Certificate of Substantial Completion. Design-Builder's notice <br /> shall include the following documents and information: <br /> 6.6.1.1 An affidavit certifying that there are no claims, obligations or liens outstanding or <br /> unsatisfied for labor, services, material, equipment, taxes or other items performed, <br /> furnished or incurred for or in connection with the Work through the date of the notice which <br /> will in any way affect Owner's interests. <br /> 6.6.1.2 All operating manuals, warranties, record documents and other deliverables <br /> required by the Contract Documents; and <br /> 6.6.1.3 A signed and stamped set of all calculations supporting the design of the Project. <br /> 6.6.2 Upon Substantial Completion of the entire Work or, if applicable, any portion of the Work, <br /> Owner shall release to Design-Builder all retained amounts relating, as applicable, to the entire <br /> GENERAL CONDITIONS OF PROGRESSIVE DESIGN-BUILD CONTRACT,Page 16 <br />