Laserfiche WebLink
I <br /> 1 Contractor, take whatever steps are necessary to correct those deficiencies pursuant to <br /> I 2 Section 1-05.7. <br /> 3 The Contractor will not be allowed an extension of contract time because of a delay in <br /> 4 the performance of the work attributable to the exercise of the Engineer's right <br /> 5 hereunder. <br /> 6 <br /> 7 Upon correction of all deficiencies, the Engineer will notify the Contractor and the <br /> I 8 Contracting Agency, in writing, of the date upon which the work was considered physically <br /> 9 complete. That date shall constitute the Physical Completion Date of the contract, but shall <br /> 10 not imply acceptance of the work or that all the obligations of the Contractor under the <br /> 11 contract have been fulfilled. <br /> 12 <br /> 13 1-05.11(3) Operational Testing <br /> 14 <br /> 15 It is the intent of the Contracting Agency to have at the Physical Completion Date a <br /> 16 complete and operable system. Therefore when the work involves the installation of <br /> 17 machinery or other mechanical equipment; street lighting, electrical distribution or signal <br /> I 18 systems; irrigation systems; buildings; or other similar work it may be desirable for the <br /> 19 Engineer to have the Contractor operate and test the work for a period of time after final <br /> 20 inspection but prior to the physical completion date. Whenever items of work are listed in <br /> I 21 the Contract Provisions for operational testing they shall be fully tested under operating <br /> 22 conditions for the time period specified to ensure their acceptability prior to the Physical <br /> 23 Completion Date. During and following the test period, the Contractor shall correct any <br /> I 24 items of workmanship, materials, or equipment which prove faulty, or that are not in first <br /> 25 class operating condition. Equipment, electrical controls, meters, or other devices and <br /> 26 equipment to be tested during this period shall be tested under the observation of the <br /> 27 Engineer, so that the Engineer may determine their suitability for the purpose for which <br /> I28 they were installed. The Physical Completion Date cannot be established until testing <br /> 29 and corrections have been completed to the satisfaction of the Engineer. <br /> 30 <br /> I 31 The costs for power, gas, labor, material, supplies, and everything else needed to <br /> 32 successfully complete operational testing, shall be included in the unit contract prices <br /> 33 related to the system being tested, unless specifically set forth otherwise in the proposal. <br /> I 34 <br /> 35 Operational and test periods, when required by the Engineer, shall not affect a <br /> 36 manufacturer's guaranties or warranties furnished under the terms of the contract. <br /> I 37 <br /> 38 <br /> 39 <br /> I 40 1-05.13.RTF <br /> 41 1-05.13 Superintendents, Labor and Equipment of Contractor <br /> 42 (August 14, 2013 APWA GSP) <br /> 43 I <br /> 44 Delete the sixth and seventh paragraphs of this section. <br /> 45 <br /> 46 1-05.14.GR1 <br /> I 47 Cooperation With Other Contractors <br /> 48 <br /> 49 1-05.14.INSTI.GR1 <br /> 111 <br /> 50 Section 1-05.14 is supplemented with the following: <br /> I <br /> 2022 PAVEMENT MAINTENANCE OVERLAY PAGE 15 OF 85 SPECIALS <br /> WORK ORDER 3764 FEBRUARY 23,2022 <br />