Project: POE Combined Sewer Main Improvements <br /> Change Order No. 2 <br /> Change Order Effective Date: May 2, 2022 <br /> CHANGE ORDER NO. 2 COSTS <br /> Bid Item 5: $ 170,000.00 <br /> Bid Item 13: $ 253,125.00 <br /> New Item 103: $ 5,203.00 <br /> New Item 104: $ 2,485.00 <br /> Subtotal: $ 430,813.00 <br /> 0.1% Tax Increase to Existing Contract $ 3,259.28 <br /> 9.9% Sales Tax on CO No. 2 $ 42,650.49 <br /> Total CO No. 2 Costs $ 476,722.77 <br /> CONTRACT TIME <br /> There are five (5) days added to the Contract regarding the Interim Completion Date. This <br /> moves this date from May 31, 2022 to June 4, 2022. This does not affect the Contract time to <br /> reach Physical Completion, which remains one hundred-fifty (150) days. This does not affect <br /> the City-Port Agreement Expiration Date, which remains unchanged at June 30, 2022. <br />