Laserfiche WebLink
Project: Water Main Replacement"V" <br /> Change Order No. <br /> Change Order Effective Date: June 7, 2022 <br /> New Item # 102 —Provide and Install Field Lock Gaskets on 8-Inch and 12-Inch Ductile <br /> Iron Water Main Pipe. The bid set of documents did not require a bid for water main pipe <br /> using field lock gaskets, but when the "For Construction" documents were issued for <br /> construction, they were required. This new item reimburses the contractor's costs to purchase <br /> and install field lock gaskets on this project. <br /> Sales Tax <br /> The City of Everett Sales Tax went up from 9.8%to 9.9% on April 1, 2022. To bring this <br /> Contract to the current sales tax rate of 9.9%, the remaining Contract total will be taxed an <br /> additional 0.1%. <br /> Contract Subtotal Excluding Sales Tax $1,752,281.20 <br /> Contract Costs to April 1, 2022 Excluding Sales Tax $1,749,249.49 <br /> Contract Balance Excluding Sales Tax $ 3,031.71 <br /> $3,031.71(0.1%)=$3.03 <br /> Change Order No. 1 Costs <br /> Bid Item 41: $ 3,138.75 <br /> New Item 100: $ 7,845.82 <br /> New Item 101: $ 6,976.00 <br /> New Item 102: $ 5,513.00 <br /> Remaining Balance: $ 3,031.71 <br /> Subtotal: $26,505.28 <br /> 9.9% Sales Tax: $ 2,624.02 <br /> 0.1% Sales Tax $ 3.03 <br /> Total Cost $29,132.33 <br /> Contract Time <br /> There are no days added to the Contract. <br />