CITY OF EVERETT SPECIAL PROVISIONS <br /> The Baseline Schedule shall be part of the Contract. <br /> Each activity shall be identified with a number that incorporates the Specification <br /> ' section number. <br /> Activities shall be consistent and identified with the Schedule of Values (if <br /> applicable) or unit prices of the bid schedule. All elements and items in the <br /> ' Schedule of Values or unit prices in the bid schedule shall appear in the Progress <br /> Schedules. <br /> Contractor shall provide sub-schedules for each stage/phase of Work as required <br /> by City, City's Representative, or Subcontractor. <br /> Contractor shall provide sub-schedules to define major portions of the entire <br /> schedule. Include long-lead-time items for Equipment and material that requires <br /> long fabrication time. Order these well in advance of required delivery time to <br /> sequence with overall construction schedule. <br /> Each schedule shall show accumulated percentage of completion of each activity, <br /> and total percentage of Work completed, as of the date of payment application. <br /> Contractor shall include in each schedule as activities the submission, review, and <br /> correction of Submittals, Shop Drawings, Product Data and Samples. The <br /> ' schedule should show: <br /> 1. The dates for Contractor's Submittals. <br /> 2. A minimum of 14 calendar days duration for City or City's <br /> Representative's review. <br /> 3. Indicate decision data for selection of finishes. <br /> 4. Show Submittal preparation, submission, review, and breakdown at a <br /> minimum. Show individual parts of major Submittals. <br /> Contractor shall identify any and all Work furnished by City and installed by City on <br /> the construction schedule. <br /> 1-08.3(4) Measurement <br /> Delete 1-08.3(4). <br /> 1-08.3(5) Payment <br /> Delete 1-08.3(5) and substitute the following: <br /> Costs incurred in performance of this Work shall be included in the contract bid <br /> ' items and no direct compensation shall be paid. <br /> 1-08.4 Prosecution of Work <br /> Delete 1-08.4 and substitute the following: <br /> 1-08.4 Notice to Proceed and Prosecution of Work <br /> (******) <br /> The City will issue a Notice to Proceed after the Contract has been executed and the Contract <br /> Bonds and evidence of insurance have been approved and filed by the City. The Contractor <br /> shall not commence with the Work until the Notice to Proceed has been given by the City. <br /> The Contractor shall commence construction activities on the Project site within 14 calendar <br /> days of the Notice to Proceed Date, unless otherwise approved in writing. The Contractor <br /> shall diligently pursue the Work to the Physical Completion Date within the time specified in <br /> the Contract. Voluntary shutdown or slowing of operations by the Contractor shall not relieve <br /> the Contractor of the responsibility to complete the Work within the time(s) specified in the <br /> Contract. <br /> Water Main Replacement"W" Division 1 —GENERAL <br /> p REQUIREMENTS April, 2022 <br /> WO No.—UP3766 SP—97 <br />