Laserfiche WebLink
CITY OF EVERETT SPECIAL PROVISIONS <br /> 1-08.3(3) Schedule Updates <br /> Delete 1-08.3(3) and substitute the following: <br /> 1-08.3(3) Schedule Format And Content <br /> (******) <br /> 1-08.3(3)A Schedule Format <br /> All schedules shall be in the following form: <br /> 1. Network analysis system using the current version of Microsoft Project <br /> software (or other software acceptable to the City Representative) and <br /> the critical path method, as outlined in The Associated General <br /> Contractors of America (AGC) publication "The Use of CPM in <br /> Construction -A Manual for General Contractors." <br /> 2. Sequence of Listings: The chronological order of the start of each activity <br /> of Work. Listings on Progress Schedule and Schedule of Values shall be <br /> the same. <br /> 3. Scale and Spacing: To provide space for notations and revisions. 111 <br /> 4. Each schedule and update shall be provided in three (3) paper copies <br /> and one electronic copy in current Microsoft Project format (or other <br /> format acceptable to the City Representative). Paper copies shall be on a <br /> single sheet of paper and of sufficient size to allow legibility of schedule. <br /> Pieces of the schedule on separate sheets of paper that must be taped <br /> together to form schedule are not permitted. Electronic copies shall be <br /> submitted on either separate CD-ROMs or as email attachment to City's <br /> Representative or as otherwise acceptable to the City Representative. <br /> 5. Updated Progress Schedules shall indicate progress of the Work to the <br /> date of submission by drawing a vertical line down the schedule to <br /> represent Work completed to date. <br /> 1-08.3(3)B Schedule Contents <br /> All Progress Schedules shall: <br /> 1. Include essential sub-schedules of related activities. <br /> 2. Allow for timely incorporation of any other's work under separate contract <br /> with City. <br /> 3. Allow for timely incorporation of work provided and installed by City. 1 4. Include submittals to agencies required for performance of Work with <br /> sufficient, adequate and reasonable time for review, comment and return <br /> submittals. , <br /> 5. Allow for appropriate durations to complete activities that may be affected <br /> by weather during the time of year the activities are performed. <br /> 6. Identify logical connections, dependency upon preceding or succeeding I <br /> activities, restraints or constraints, planned start and completion dates, <br /> duration, actual start and completion dates, and variances. <br /> 7. Activity durations shall not exceed twenty (20) days. The activities shall 1 <br /> be related to early and late start, early and late finish, and Float dates. <br /> Activities listed in the Preliminary Schedule shall be included in all subsequent <br /> schedules. No activity in the Preliminary Schedule shall be deleted without prior <br /> written consent of the Representative and City. <br /> Contractor shall notify City's Representative and City in writing and highlight the <br /> addition of all activities to the schedule after the Preliminary Schedule. I <br /> Water Main Replacement"W" Division 1 —GENERAL REQUIREMENTS April, 2022 <br /> WO No.—UP3766 SP—96 <br />