<br /> CITY OF EVERETT SPECIAL PROVISIONS
<br /> DIVISION B - BID ITEM DESCRIPTIONS
<br /> Bid Item 1 - Mobilization
<br /> Measurement and Payment: Lump Sum (LS)
<br /> The lump sum bid for mobilization shall constitute complete compensation for all of
<br /> Contractor's preconstruction costs of preparatory work and operations including, but not
<br /> limited to, those necessary for the movement of the Contractor's personnel, equipment,
<br /> supplies and incidentals to the Project; for the establishment of its offices, buildings and
<br /> other facilities necessary for Work on this Project; for premiums on bonds and insurance for
<br /> the Project, and for Work and operations that the Contractor must perform or costs it must
<br /> incur before beginning production work on the various items on the Project. Mobilization
<br /> also includes, but is not limited to, posting construction identification signs, securing
<br /> permits, establishing safety and security measures, preparing a traffic control plan(s),
<br /> preconstruction photographs, developing a Schedule of Values for lump sum bid items,
<br /> submitting the project schedule and providing product and material submittals. Also include
<br /> mobilization costs for all subcontracted work along with all costs for utility coordination
<br /> noted on the Plans and in the Specifications.
<br /> Items not included in this item include, but are not limited to:
<br /> (a) Work covered by a specific bid item or Work that is to be included in a bid item
<br /> or items.
<br /> (b) Profit, interest on borrowed money, overhead or management costs.
<br /> Partial payments will be made for the lump sum contract price for"Mobilization" as follows:
<br /> (a) When 5% of the total original contract amount is earned from other bid items,
<br /> 50% of the amount bid for mobilization, or 5% of the total original contract
<br /> amount, whichever is the least, will be paid.
<br /> (b) When 10% of the total original contract amount is earned from other bid items.
<br /> 100% of the amount bid for mobilization, or 10% of the total contract amount,
<br /> whichever is the least, will be paid.
<br /> Upon completion of all work on the project, payment of any amount bid for mobilization in
<br /> excess of 10% of the total original contract amount will be paid.
<br /> Bid Item 2 - Surveying
<br /> Measurement and Payment: Lump Sum (LS)
<br /> Measurement for surveying will be the ratio of actual pipe installed and backfilled to the
<br /> total quantity of pipe listed in the Proposal.
<br /> The lump sum bid for surveying includes, but is not limited to, all costs associated with
<br /> furnishing all labor, tools, survey instruments materials, and other equipment necessary for
<br /> the setting and monitoring the location, elevation, alignment and grade of the Work as
<br /> specified in 1-05.4 CONFORMITY WITH AND DEVIATIONS FROM PLANS AND STAKES
<br /> and the Plans.
<br /> The lump sum bid item also includes, but is not limited to, all costs associated with
<br /> furnishing all labor, tools, survey instruments, materials and other equipment necessary for
<br /> verifying the rim and invert elevations, prior to construction, of all existing manholes and
<br /> pipes where connections are to be made.
<br /> The lump sum also includes, but is not limited to, all costs associated with furnishing all
<br /> labor, tools, survey instruments, materials and other equipment necessary for obtaining the
<br /> "as constructed" location and elevations of the Work, in particular, sewer pipe invert
<br /> elevations and other information necessary for production of the Record Drawing (As-
<br /> Water Main Replacement"W" Division B—BID DESCRIPTIONS April,2022
<br /> WO No.—UP3766 SP-3