I <br /> City of Everett 00 72 00 - 15 <br /> i <br /> 4.5.2. Suggestions to Contractor <br /> ' Nothing in these Contract Documents requires the Owner's Representative to provide the Contractor with <br /> direction or advice on how to do the Work,construction practices,or means and methods. If the Owner's <br /> Representative approves, suggests or recommends any construction practice,means,method or manner <br /> for doing the Work or producing materials,the approval or recommendation shall not: (A)guarantee that <br /> following the method or manner will result in compliance with the Contract Documents;(B)relieve the <br /> Contractor of any risks or obligations under the Contract Documents;or(C)create any liability by the <br /> Owner to the Contractor. <br /> Suggestions as to the plans or methods of accomplishing the Work or Contract requirements by the <br /> Owner or the Owner's Representative to the Contractor but not specified or required,if adopted or <br /> followed by the Contractor in whole or in part,shall be used at the risk and responsibility of the <br /> Contractor. The Owner and the Owner's Representative assume no responsibility therefor and in no way <br /> will be held liable for any defects in the Work which may result from or be caused by use of such plan or <br /> method or Work. <br /> 4.5.3 Meetings with Owner <br /> The Contractor shall have its duly authorized representative attend periodic informational meetings with <br /> the Owner's Representative and City staff,as reasonably required by the Owner. <br /> Contractor,Owner,and Owner's Representative shall meet as often as determined by the Owner's <br /> Representative,but no less often than once each month. The purpose of the meeting is to review Project <br /> status in relation to the construction schedule;review value of Work completed during the previous <br /> month; and,if applicable,review Contractor's plans to return Project status to that required by the <br /> schedule. If requested by the Owner or Owner's Representative,the Contractor shall submit a written <br /> progress report within five(5)days following this meeting,comprising: <br /> 1. The current construction schedule indicating percent complete,actual completion or start dates <br /> since the previous review,the estimated remaining duration for each activity in progress, <br /> Schedule of Values update,and narrative summary. <br /> 2. Reasons any activities are behind schedule and the corrective steps being taken. <br /> 4.5.4. Cooperation with Others <br /> The Contractor agrees to permit entry to the Site of the Work by the Owner,its employees or other <br /> contractors performing work on behalf of the Owner. The Contractor shall afford to the Owner,other <br /> contractors and their employees,reasonable facilities and cooperation and shall arrange its work and <br /> dispose of its materials in such a manner as to not interfere with the activities of the Owner or of others <br /> upon the Site of Work. The Contractor shall promptly make good any Contractor-caused injury or <br /> damage to persons or property that may be sustained by other contractors or employees of the Owner. <br /> The Contractor shall join its work to that of others and perform its work in proper sequence in relation to <br /> that of others. <br /> If requested by the Contractor,the Owner will arrange meetings with other contractors performing work <br /> on behalf of the Owner to plan coordination of construction activities. The Contractor shall inform itself <br /> of the planned activities of other contractors and will coordinate its work with the other contractors. <br /> Contractor shall notify the Owner of problems,interference or any difficulty with other contractors or <br /> ' workers engaged by the Owner. The Notice shall be sufficiently prompt and specific so as to allow the <br /> Owner to mitigate or avoid increased costs,time of performance,damages or injury. Contractor's failure <br /> to provide such Notice in a timely way shall be deemed a waiver and release of any and all Contract <br /> ' Claims relating to,arising out of,or caused by,any alleged interference,difficulty or problem with <br /> another contractor or worker engaged by the Owner. <br /> 00 72 00 - 15 GENERAL CONDITIONS <br />