My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
IMCO General Construction 12/13/2022
>
Contracts
>
Capital Contract
>
Capital Construction Contracts and Change Orders
>
IMCO General Construction 12/13/2022
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
7/30/2025 12:23:45 PM
Creation date
12/30/2022 2:22:28 PM
Metadata
Fields
Template:
Contracts
Contractor's Name
IMCO General Construction
Approval Date
12/13/2022
Council Approval Date
11/2/2022
Department
Public Works
Department Project Manager
Zach Brown
Subject / Project Title
Water Filter Plant Portal 4 Improvements
Public Works WO Number
UP3755
Tracking Number
0003541
Total Compensation
$4,520,327.00
Contract Type
Capital Contract
Contract Subtype
Capital Construction Contracts and Change Orders
Retention Period
10 Years Then Transfer to State Archivist
Imported from EPIC
No
Document Relationships
IMCO General Construction 7/30/2025 Change Order 4
(Contract)
Path:
\Documents\City Clerk\Contracts\Capital Contract\Capital Construction Contracts and Change Orders
IMCO General Construction 9/5/2024 Change Order 2
(Contract)
Path:
\Records\City Clerk\Contracts\10 Years Then Transfer to State Archivist\2024
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
978
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
I <br /> City of Everett 00 72 00 - 51 <br /> Water Filter Plant Portal 4 Improvements WO# 3755 <br /> 12.4.3.5.2.1 Resources <br /> To demonstrate the Contractor could not and did not use resources,including but not limited to <br /> labor,materials and equipment from this Project for any other work on this or any other project <br /> during the period of delay(12.4.3.5.2.(3)),the Contractor must: <br /> ' a. Affirmatively represent and warrant that it did not perform substitute Work; <br /> b. Identify the specific resources that were idled;and <br /> c. Show that those resources did not,and could not,work on other contracts or projects during <br /> the Delay. <br /> 12.4.3.5.2.2 No Material Variations <br /> To demonstrate the Contractor's Overhead costs did not materially vary from its usual seasonal <br /> Overhead costs during the period of delay(12.4.3.5.2.(4)),the Contractor must; <br /> a. Affirmatively represent and warrant that the completion of the subject Work was extended <br /> and that such extension prevented the performance of other work during both the period of <br /> delay and the later period of time required to complete the extended Work, <br /> b. Disclose the details of Contractor generated billings and Contractor Overhead Costs(as <br /> hereinafter defined)throughout the actual project performance. The details of such <br /> information should be no less than specific identification of the sources and amounts of <br /> revenue on no greater than a monthly basis and specific identification of the types and <br /> amounts of Contractor Overhead Costs on no greater than a monthly basis for the actual <br /> Project duration. <br /> 12.4.3.5.2.3 Overabsorbed Overhead <br /> To demonstrate that it did not incur Overabsorbed Overhead in the period following the Delay <br /> (12.4.3.5.2.(5)),the Contractor must: <br /> a. Affirmatively represent and warrant that completion of the delayed Work prevented the <br /> performance of other work; <br /> b. Identify the critical resource unavailable for other work due to completion of the delayed <br /> Contract;and <br /> c. Showing that unavailability of this critical resource precluded the performance of other work. <br /> 12.4.4 Inefficiencies <br /> 12.4.4.1 Adjustment of Contract Sum <br /> To the extent Contractor is entitled to an increase in Contract Sum because of inefficiencies or impaired <br /> productivity,then compensation due,if any,shall be calculated as provided in_9.7._Equitable9.5. <br /> ADJUSTMENT OF CONTRACT SUM. There is no entitlement to increase in Contract Sum for <br /> inefficiencies related to a Third Party or to a Force Majeure Event. <br /> 12.4.4.2 Adjustment of Contract Time <br /> To the extent Contractor is entitled to an extension of Contract Time because of inefficiencies or impaired <br /> productivity,then the time extension,if any,shall be determined as provided in 5.2.2.2 Extensions of <br /> Contract Time. <br /> I <br /> I <br /> I <br /> 00 72 00 - 51 GENERAL CONDITIONS <br />
The URL can be used to link to this page
Your browser does not support the video tag.