ID Task <br />Mode <br />Task Name Duration Start Finish Predecessors <br />1 Reservoir 3 Design-Bid Build 790 days Tue 1/3/23 Tue 2/10/26 <br />2 NTP 0 days Tue 1/3/23 Tue 1/3/23 <br />3 Kick-Off Meeting/Site Visit 0 days Thu 1/5/23 Thu 1/5/23 2FS+2 days <br />4 Preliminary Design Report (PDR)135 days Mon 1/9/23 Tue 7/18/23 <br />13 Phase 1 Design/Construction 470 days Mon 3/27/23 Thu 1/30/25 <br />14 Design Phase 170 days Mon 3/27/23 Wed <br />11/22/23 <br />15 30% Design Phase 70 days Mon 3/27/23 Wed 7/5/23 <br />20 60% Design Phase 40 days Wed 7/19/23 Wed 9/13/23 <br />24 90% Design Phase 30 days Thu 9/14/23 Wed <br />10/25/23 <br />28 Prepare Bid Documents 30 days Thu 10/12/23 Wed <br />11/22/23 <br />27 <br />31 Bid Phase 40 days Mon 11/27/23Tue 1/23/24 <br />36 Construction Phase 260 days Wed 1/24/24 Thu 1/30/25 <br />45 Phase 2 Design/Construction 431 days Thu 5/30/24 Tue 2/10/26 <br />46 Design Phase 115 days Thu 5/30/24 Fri 11/8/24 <br />47 30% Design Phase 35 days Thu 5/30/24 Thu 7/18/24 <br />51 60% Design Phase 35 days Fri 7/19/24 Fri 9/6/24 <br />55 90% Design Phase 25 days Mon 9/9/24 Fri 10/11/24 <br />59 Prepare Bid Documents 30 days Mon 9/30/24 Fri 11/8/24 <br />62 Bid Phase 41 days Wed 11/13/24Wed 1/15/25 <br />67 Construction Phase 270 days Mon 1/20/25 Tue 2/10/26 <br />1/3 <br />1/5 <br />Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 <br />2023 2024 2025 2026 <br />Task <br />Split <br />Milestone <br />Summary <br />Project Summary <br />Inactive Task <br />Inactive Milestone <br />Inactive Summary <br />Manual Task <br />Duration-only <br />Manual Summary Rollup <br />Manual Summary <br />Start-only <br />Finish-only <br />External Tasks <br />External Milestone <br />Deadline <br />Progress <br />Manual Progress <br />Page 1 <br />Project: Reservoir 3 Implementa <br />Date: Thu 7/7/22 <br />Reservoir 3 Design-Bid-Build Summary Schedule