ID Task <br />Mode <br />Task Name Duration Start Finish Predecessors <br />43 Tank Construction 200 days Wed 3/20/24 Thu 1/2/25 41FF <br />44 Tank Commissioning 20 days Fri 1/3/25 Thu 1/30/25 43 <br />45 Phase 2 Design/Construction 431 days Thu 5/30/24 Tue 2/10/26 <br />46 Design Phase 115 days Thu 5/30/24 Fri 11/8/24 <br />47 30% Design Phase 35 days Thu 5/30/24 Thu 7/18/24 <br />48 Prepare 30% Design <br />Documents <br />25 days Thu 5/30/24 Wed 7/3/24 9FS+285 days <br />49 City Review of 30% Design10 days Fri 7/5/24 Thu 7/18/24 48 <br />50 30% Design Workshop 0 days Thu 7/18/24 Thu 7/18/24 49 <br />51 60% Design Phase 35 days Fri 7/19/24 Fri 9/6/24 <br />52 Prepare 60% Design <br />Documents <br />25 days Fri 7/19/24 Thu 8/22/24 50,12 <br />53 City Review of 60% Design10 days Fri 8/23/24 Fri 9/6/24 52 <br />54 60% Design Workshop 0 days Fri 9/6/24 Fri 9/6/24 53FF <br />55 90% Design Phase 25 days Mon 9/9/24 Fri 10/11/24 <br />56 Prepare 90% Design <br />Documents <br />15 days Mon 9/9/24 Fri 9/27/24 54 <br />57 City Review of 90% Design10 days Mon 9/30/24 Fri 10/11/24 56 <br />58 90% Design Workshop 0 days Fri 10/11/24 Fri 10/11/24 57FF <br />59 Prepare Bid Documents 30 days Mon 9/30/24 Fri 11/8/24 <br />60 DOH Review for <br />Concurrance of Design <br />20 days Mon 9/30/24 Fri 10/25/24 56 <br />61 Finalize Bid Documents 10 days Mon 10/28/24Fri 11/8/24 58,60 <br />62 Bid Phase 41 days Wed 11/13/24Wed 1/15/25 <br />63 Advertise for Bid 20 days Wed 11/13/24Fri 12/13/24 64SF <br />7/18 <br />9/6 <br />10/11 <br />Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 <br />2023 2024 2025 2026 <br />Task <br />Split <br />Milestone <br />Summary <br />Project Summary <br />Inactive Task <br />Inactive Milestone <br />Inactive Summary <br />Manual Task <br />Duration-only <br />Manual Summary Rollup <br />Manual Summary <br />Start-only <br />Finish-only <br />External Tasks <br />External Milestone <br />Deadline <br />Progress <br />Manual Progress <br />Page 3 <br />Project: Reservoir 3 Implementa <br />Date: Thu 7/7/22 <br />Reservoir 3 Design-Bid-Build Detail Schedule