<br /> <br /> <br /> <br /> <br /> <br />Change Order No. 1 <br />Change Order Effective Date: March 13, 2023 <br /> <br /> <br /> <br />EXHIBIT A—DESCRIPTION OF CHANGED WORK <br /> <br />This Change Order No. 1 modifies one (1) existing bid item and adds five (5) new items <br />to the Contract, as described below. <br /> <br /> <br />MODIFIED BID ITEMS <br /> <br /> <br />Bid Item # 8 – Foundation Material, Class A or B. Modify bid item entitled, <br />“Foundation Material, Class A or B” at the bid item unit price of $150.00/Ton, by adding <br />25 Tons to the Contract, resulting in a Contract increase of $3,750.00. <br /> <br /> <br />ADDED ITEMS <br /> <br /> <br />New Item # 100 – Open Cut and Remove portion of 60-Inch Reinforced Concrete <br />Pipe (RCP). Add new item entitled, “Open Cut and Remove portion of 60-Inch <br />Reinforced Concrete Pipe (RCP)” at the agreed to Lump Sum Price of $80,000.00, <br />resulting in a Contract increase of $80,000.00. This work included the following: Install <br />sumps & pumps, remove 60-Inch RCP to springline, keep fuel in generator, Vactor work <br />around underground electrical power, set up additional pump system, clean & service <br />pumps, monitor pumps during low & high tide, install additional shoring, over excavate <br />sides of 60-Inch RCP, implement steel sheets for additional shoring, remove shoring <br />boxes & rebuild them from 10 foot spreaders to 12 foot spreaders, build grout dam, and <br />remove 60-Inch grout plug & replace with new plug. <br /> <br />New Item # 101 – Additional Backfill of 60-Inch RCP. Add new item entitled, <br />“Additional Backfill of 60-Inch RCP” at the agreed to Lump Sum Price of $10,000.00, <br />resulting in a Contract increase of $10,000.00. <br /> <br />New Item # 102 – Remove and Dispose of Concrete Rubble and Remove Steel <br />Sheets. “Add new item entitled, “Remove and Dispose of Concrete Rubble and <br />Remove Steel Sheets” at the agreed to Lump Sum Price of $12,500.00, resulting in a <br />Contract increase of $12,500.00. This work included the following: Load and export <br />concrete rubble from site, place 4”x8” spalls, return steel sheets to vendor, breakdown <br />generator pump, remove plastic, remove sandbags, and place ecology block over 60- <br />Inch RCP. <br /> <br /> <br />