SECTION 01 29 76 <br /> PROGRESS PAYMENTS -GCCM <br /> PART 1 —GENERAL <br /> 1.1 SUMMARY <br /> A. This section includes the administrative and procedural requirements for Contractor <br /> progress payment and release of retainage as herein specified and further described <br /> in Article 9 of the General Conditions. <br /> B. Owner's forms referenced in this section include (see Appendix A): <br /> 1. Application and Certificate for Payment on Contract (Application for Payment). <br /> 2. Schedule of Values <br /> 3. Monthly Subcontractors List and Certifications. <br /> 4. Statement of Intent to Pay Prevailing Wages <br /> 5. Certificate of Payment of Labor and Materials. <br /> 1.2 PREREQUISITES FOR FIRST APPLICATION FOR PAYMENT <br /> A. Prevailing Wage Forms: Submit a Statement of Intent to Pay Prevailing Wages form, <br /> approved by the Department of Labor and Industries, prior to commencing the Work <br /> (see Article 9.5.3 of the General Conditions) The Owner will not make payment on an <br /> Application for Payment until the Contractor has filed with the Owner an approved copy <br /> of the form for the Contractor and every Subcontractor of every tier that performed work <br /> during the payment period and are included in an Application for Payment. The form <br /> shall list every classification of laborer,worker, or mechanic employed by the Contractor <br /> and Subcontractors. There are no exceptions to this requirement. <br /> 1. The website address link to the prevailing wage forms is included in Appendix A. <br /> 2. The website address link to the'Washington State Prevailing Wage Rates for Public <br /> Works Contracts" is included in GCCM Contract—Attachment C. <br /> B. Schedule of Values: At least 14 days before submitting the first Application for Payment, <br /> submit and receive approval of the Schedule of Values allocating the detail of the entire <br /> GMP, in a breakdown acceptable to the Architect and Owner, which shall be <br /> documented on the Application for Payment see 1.6.A.5 "Building Componentization <br /> Report" in this Section for additional Final Completion construction cost reporting <br /> requirements. The approved Schedule of Values will be used by the Architect and <br /> Owner as the basis for progress payments. Payment for work will only be made for, <br /> and in accordance with,those items included in the approved schedule of values. <br /> 1. Format: On 8-1/2-inch by 11-inch paper. <br /> 2. Make sum of total scheduled costs equal to the Total Contract Cost. Do not include <br /> State of Washington sales tax. <br /> City of Everett Municipal Building February 3, 2023 <br /> Everett Municipal Building Public Works Tenant 01 29 76-1 Spec Sect 01 29 76 <br /> Improvements Progress Payments-GCCM <br /> RFFP for GC/CM Services <br />