City of Everett 00 72 00 - 43 <br /> 6. An event occurs,or fails to occur,that the Contractor believes,or should reasonably foresee,may <br /> ' result in a Contract Claim; <br /> the Contractor shall immediately give Notice to the Owner or Owner's Representative as provided in this <br /> section and elsewhere in the General Conditions and Specifications. <br /> ' Timely and adequate Notice is a condition precedent to a Contract Claim. <br /> Requests for extensions of Contract Time must be made and will be evaluated in accordance with 5.2.2.2 <br /> Extensions of Contract Time. <br /> ' Irrespective of any request for additional compensation or Contract Time or any Contract Claim that work <br /> is extra and not part of the original scope of Work,the Contractor shall proceed expeditiously and <br /> ' promptly with the work as the Owner orders. <br /> If the Contractor fails to follow the procedures of this Contract,including failing to give Notice,the <br /> Contractor completely waives such Contract Claim. In its sole discretion,the Owner may waive strict <br /> compliance with procedures,but any such waiver of one or more items or elements does not waive the <br /> ' necessity for Contractor's strict compliance with any other item or element,nor shall such waiver be <br /> admissible in any legal proceeding for any reason. <br /> ' 10.2 FORM OF NOTICE <br /> The Notice must include the following minimum information: <br /> 1. A complete and accurate description of the event or events giving rise to the Notice,including <br /> ' dates,times,and locations; <br /> 2. A preliminary list of persons of involved in such event; <br /> 3. A statement whether the Contractor believes the event may result in a Contract Claim for <br /> additional Contract Time or adjustment of the Contract Sum; <br /> 4. A date by which Contractor shall begin providing Supplemental Information as provided in this <br /> ' section. <br /> 10.3 SUPPLEMENTAL INFORMATION <br /> ' Contractor shall supplement the written Notice as soon as possible with a written statement providing the <br /> following: <br /> 1. The date of the event, incident,direction, and other pertinent information; <br /> 2. The nature and circumstances giving rise to the Notice; <br /> 3. The Contract provisions relating to,but not limited to,the event,incident,and direction; <br /> 4. The estimated dollar cost,if any,of the Extra Work,or Delay,or both and how that estimate was <br /> determined; and <br /> 5. An analysis of the schedule showing the schedule change or disruption if the Contractor is <br /> asserting a schedule change or disruption. <br /> ' Throughout any work related to a Notice,the Contractor shall keep complete and accurate records of <br /> costs,expenses,and time incurred for which Contractor will or may seek an adjustment. Contractor <br /> waives and is stopped from seeking an adjustment of Contract Sum or Contract Time where Contractor <br /> fails to keep and maintain cost,timekeeping,and scheduling records segregated and contemporaneously <br /> allocated to the subject work for which an adjustment is sought. For example, failure to keep <br /> contemporaneous labor and equipment time records specifically and only allocated to each item of <br /> claimed Extra Work shall constitute a waiver of any Contract Claim for reimbursement or additional <br /> Contract Time for each such item of Extra Work. The Contractor shall permit the Owner access to these <br /> and any other records needed for evaluating requests for additional Contract Time or Contract Sum. <br /> 00 72 00 - 43 GENERAL CONDITIONS <br />